Targets and objectives page 27:
Debt Financing Completion: 4Q/14-1Q/15 (2Q-4Q/14 Aug presentation)
Mine Construction and Start-up 1H/15 → 2H/16 (2H/14 → 2H/16 Aug presentation)
Ramp up to full production 4Q/17-1Q/18 (2H/17 Aug presentation)