"Since the company's last report, the company experienced a minor shutdown in May, 2008, to activate its expanded trucking terminal."
I can't seem to locate the pictures now on Connacher's Web site. Anyone know where they're at? I'm curious about the trucking terminal, where it is, pictures and etc.
"In June, 2008, production was constrained while managing some minor issues related to the vapor-recovery unit and then the plant was shut down for several days for an unscheduled turnaround to clean out vessels, which had experienced material buildup since the start-up of the plant."
What's meant by vessels that had to be cleaned out? Is this probably something that was an issue due to startup material clogging that shouldn't happen very often, or something that's a normal business occurrance?