I'm afraid patience goes with the territory for these projects. I got so bored I went back and tried to document the timelines. 17 months from Order in Council until first production at Great Divide. Hopefully that GD experience gained, plus prefabricated assemblies, will speed things up at Algar.
Great Divide
Application filed |
08/17/05 |
|
|
EUB approval letter |
06/29/06 |
|
|
Order in Council |
07/13/06 |
330 |
days from application |
Commenced steam injection |
09/17/07 |
|
|
First stage full-time production |
12/19/07 |
854 |
days from application |
|
|
524 |
days from Order in Council |
Algar
Application filed |
06/19/07 |
|
|
Verbal approval notification |
10/01/08 |
|
|
Order in Council |
11/06/08 |
506 |
days from application |
Commenced steam injection |
|
|
|
First stage full-time production |
|
|
|