From what I can read the Feasibility doesn't recommend 10,000 meters of drilling in Phase 1 or in Phase 1 & 2 combined. The presentation is emphasizing moving the waste into measured. Elmer said something about how that would be done as part of the work Teck was about to do. They did say that Teck was going East to test the anomaly, whereas the FS seems to be emphasizing the West and North of Paramount. I guess we have to wait for a more detailed description of the work that is intended. The FS also recommended another Titan survey "eastwards towards Mount LaCasse."
The Presentation suggests:
-Undertake a diamond drilling program to determine the extent to which the
171.16 million tonnes of Inferred Resource within the pit shell can be upgraded
to a Measured or Indicated Resource.
-Drill east of current Resource Block Model to test area treated as waste in
the Feasibility Study.
The Feasibility study says:
Phase I is designed to focus on exploring and delineating the new mineralized zones
and chargeability anomalies identified in the Quantec Titan and High Resolution
Magnetic surveys, and to infill drill part of the northern portion of the Paramount Zone
in order to upgrade the resource category from inferred to indicated. Phase I will
entail a combination of diamond drilling and geophysical surveying.