Welcome To the Copper Fox Metals Inc. HUB On AGORACOM

CUU own 25% Schaft Creek: proven/probable min. reserves/940.8m tonnes = 0.27% copper, 0.19 g/t gold, 0.018% moly and 1.72 g/t silver containing: 5.6b lbs copper, 5.8m ounces gold, 363.5m lbs moly and 51.7m ounces silver; (Recoverable CuEq 0.46%)

Free
Message: Another Stupid Rumour

The Feasibility had a Project Execution Plan that outlined expected dates that can show us the order of work. It shows the access road coming a long time after the EA. I'm not sure I understand this because you would think, as CG said, that you first need a road and it is not scheduled for two years after the permits.

PROJECT EXECUTION PLAN
The project execution plan includes the following key milestones:
• receipt of remaining environmental approvals and permits:
-federal EA approval–January 2014
-construction permits–June 2014
• procurement of long-lead equipment:
-begin to issue purchase orders for grinding mills, crushers, mill motors and main transformers–July2013
-order major mining equipment–April 2014
-completion of BC Hydro’s Northwest Transmission Line at Bob Quinn substation–March 2014
•construction activities:
mobilize to site–July 2014
complete access road–March 2016
complete power line to site–January 2018
commence pre-production stripping–March 2016
complete construction for initial stage of TSF–September 2018
commission process plantfor Phase 1–December 2019
commission process plant for Phase 2–July 2020
commercial production–January 2020
Share
New Message
Please login to post a reply