Ballpark numbers when modeling the current 2021 PEA cash flows:
- Only increasing the current free cash flows by 25% could add another $700M US
- Only increasing the mine life from 21 to 35 years could add another $400M US
- Only reducing the construction timeline 1 year could add another $100M US
- All the above combined could add another $200M US
- Using $3.50 US for the LT copper price could add another $250M US (more with all the above)
- Using $3.75 US for the LT copper price could add another $250M US (more with all the above)
Current NPV (8%) is $842M US
Potential NPV (8%) @ $3.75 US = $2.75B US
CF potential NAV (8%) @ $3.75 US = $687.5M US
- Add $50M US for the carried interest
- Add $40M CAD for the milestone payments.
Total: $1B CAD for our 25%