i earlier thought that revemin might play a role in processing LC ore (the new open pit design assures a 40k ton per day capacity min imo) and this is from the latest MDA mine plan..
19.2 Processing
Processing facilities detailed in 2005 (SNC-Lavalin, 2005a) will require modifications due the increased
reserves and enlarged pit. Because the newly designed pit comes within 30m of the crusher, the crusher
location and access to the crusher will require additional study and review and may require modification.
Otherwise, see SNC-Lavalin (2005) for details.
now, i'm not so sure....it makes more sense for kry to process all the ore onsight (if they can) and the revemin mill has been mentioned as a possible "social program" in the past....this whole revimen thing might just be the "improved social program" part of minambs demands........could it be that simple?