Welcome to the Crystallex HUB on AGORACOM

Crystallex International Corporation is a Canadian-based gold company with a successful record of developing and operating gold mines in Venezuela and elsewhere in South America

Free
Message: Re: This is a great Board for DD
3
Jul 08, 2009 04:18PM
1
bmh
Jul 08, 2009 04:53PM
4
Jul 08, 2009 06:57PM
3
Jul 08, 2009 07:00PM
1
Jul 08, 2009 07:04PM
1
Jul 08, 2009 07:07PM
5
Jul 09, 2009 01:32AM
2
Jul 09, 2009 01:44AM
4
Jul 09, 2009 11:43AM
2
Jul 09, 2009 12:10PM

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

1

FEASIBILITY STUDY

LAS CRISTINAS GOLD PROJECT

Bolivar State, Venezuela

September 2003

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

2

EXECUTIVE SUMMARY

1.1 Introduction

In response to a verbal request from Crystallex International Corporation (Crystallex),

in December, 2002, SNC-Lavalin Engineers & Constructors (SNC-Lavalin) submitted

a proposal dated January 10, 2003 to prepare a feasibility study for the Las Cristinas

gold project. The feasibility study proposal was accepted on February 6, 2003 and

SNC-Lavalin was authorized to proceed with the project immediately. A formal

contract for the feasibility study has been executed.

Section 2.2 of this report summarizes the terms of reference of SNC-Lavalin and

other participants in the study. The terms of reference and scope of services are

conventional for the type of study completed, one that could be presented to financial

institutions for the purpose of raising financing to construct and commission the

project.

The key findings of the Las Cristinas Gold project are summarized in the bullet points

below and explained in more detail in the body of the report:

Location Bolivar State, South Eastern Venezuela

Mineralization 2% to 5% sulphides (pyrite and chalcopyrite)

Reserves 246 million t (1.29 g/t average grade,10.2 million oz.)

Gold Recovery 89.0 %

Gold Recovered 9.1 million ounces

Annual Gold Production

o

266,000 oz. life of mine

o

311,000 oz. first five years

Operating Cost $6.70/t ($182/oz without royalty, $196/oz with

royalty)

Capital Cost $243 million (excludes $38 million of refundable VAT)

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

3

Sustaining Capital $160 million (without VAT)

Mine Life 34 years

Mining Equipment Trucks and Shovels

Mine Stripping Ratio 1.34 to1

Process Plant Conventional Gravity and Carbon-in Leach

At a gold price of $325/oz the project is estimated to have the following results:

Before Tax After Tax

o

IRR 13.8% 10.5%

o

Net Cash Flow $742.4 million $515.9 million

o

NPV at 5% $238.5 million $139.7 million

o

Payback 4.7 years 6.9 years

Environmental Risks

o

Effluent Discharge Low

o

Tailings Dam Failure Low

o

Closure Challenges Low

o

Acid Generation Potential Low to Marginal

o

Permitting expected to be straight forward

The report was prepared by SNC-Lavalin with input from others and also Crystallex,

through the provision of numerous technical reports. Sections of the report that have

been primarily prepared by others are as noted below:

Section 3 Property Description and Location Mine Development Associates MDA)

Section 4 Geology, Mineral Resources and

Mineral Reserves

Mine Development Associates (MDA)

Section 5 Mining Mine Development Associates (MDA)

Section 6 Metallurgy J.G. Goode and Associates

Section 10 Administration and Operations Harapiak-Buckland

Section 13 Project Economics SNC-Lavalin Capital

On behalf of Crystallex MDA carried out confirmatory drilling, a review of the geology,

reserves estimates were computed and a mine plan was developed; SGS Lakefield

Research (Lakefield) ran a metallurgical carbon-in-leach pilot plant for 21 days

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

4

treating 1 tonne of representative drill core; SNC-Lavalin completed preliminary

engineering design of the major facilities. Where other sources of information have

been used in preparing this report they are referred to in the applicable sections.

1.2 Property Description and Location

The Las Cristinas Property consists of 4 contiguous concessions (LC 4-5-6-7)

totaling 3,885.6 hectares. The property is located in Bolivar State, southeastern

Venezuela, 6 km west of the village of Las Claritas and approximately 670 km

southeast of Caracas. Access to the property is via Troncal 10, the main paved

highway linking Puerto Ordaz with the Brazilian border. A soon to be upgraded 19

km unpaved road will connect Troncal 10 to the Las Cristinas camp. Current access

is via a 6 km dirt road from Las Claritas. An air strip at Las Cristinas allows for the

landing of small aircraft. Commercial airstrips are located at El Dorado and Luepa, 80

km north and south , respectively, relative to Las Cristinas. The concessions are

located in flat terrain at elevations ranging from 130 m to 160 m above sea level. The

climate is tropical and humid.

On September 17, 2002, Crystallex and the Compañia Venezolana de Guayana

(CVG) signed a Mining Operation Contract (MOC) for the development of Las

Cristinas 4, 5, 6 and 7. The MOC provides Crystallex with the exclusive right to

explore, design and construct facilities, exploit, process and sell gold from Las

Cristinas. An official translated version of the MOC is available on the Company’s

website (

www.crystallex.com

).

The MOC has been entered into in accordance with applicable Venezuelan laws and

under authority granted to the CVG by the Ministry of Energy and Mines. A report in

late February, 2003 from the Commission of Energy and Mines of the National

Assembly of Venezuela confirms the legal and administrative process by which the

contract rights of Minca, a previous partner with the CVG, were terminated. The

report also confirms the process by which the related assets were acquired by the

Republic of Venezuela, and by which the government, through the CVG, entered into

the Mining Operation Contract with Crystallex.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

5

1.3 Geology and Resources

1.3.1 Geology and Mineralization

The Las Cristinas property is located in a part of the Archean to early Proterozoic

granite-greenstone terrain of the Guayana Shield. Supracrustal sequences on the

property are predominantly intermediate metavolcanic and pyroclastic rocks. Several

rock types intrude the stratigraphic package; some post-date the mineralization.

There are two main deposits at Las Cristinas: Conductora/Cuatro Muertos and

Mesones/Sofia. At Conductora/Cuatro Muertos, gold and copper mineralization are

associated with pyrite-chalcopyrite disseminations, veinlets (2-5% sulfides) and blebs

generally oriented parallel to the foliation, which strikes north-northeast and dips

moderately to steeply west to southwest. The occurrence of sulfide mineralization is

not associated with any particular rock type, but rather, with alteration assemblages

that include secondary biotite and a younger carbonate-epidote assemblage. On a

microscopic scale, gold can be found as free grains in quartz and as blebs and

fracture fillings in pyrite and/or chalcopyrite. Silicate-carbonate-sulfide veins tend to

parallel foliation. At Mesones/Sofia, gold-copper mineralization occurs within

tourmaline breccia zones, which have obliterated primary tuffaceous textures.

Sulfide concentrations are coarser grained and more chalcopyrite rich than those at

Conductora/Cuatro Muertos.

Extensive weathering has led to the development of saprolite to depths of over 90 m

locally. The upper part of the saprolite is oxidized. Within the oxidized saprolite,

copper has been predominantly leached, but the gold remains generally in its original

distribution. The sulfide saprolite, which has been enriched in copper leached from

the overlying oxide saprolite, also retains the original gold distribution. Copper and

gold grade distributions in the bedrock have not been affected by weathering.

Data and Verification

Under the terms of the September 2002 agreement between Crystallex and the CVG

Crystallex obtained an electronic database from CVG, which included drill,

topographic, geologic, and engineering data.. Presently, data from 1,174 drill holes

and 108 trenches are included in the Las Cristinas database (Table 1-1).

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

6

Table 0-1 Drill Data Description

Data Data

Drill holes 1,174

Meters of drilling* 160,600

Gold assays 162,806

Copper assays 145,547

Copper CN Soluble

assays

40,655

Silver assays 145,221

Trenches 108

*Includes trenches

Mine Development Associates (MDA) visited the Las Cristinas site in October 2002

and found drill pads, drill collars, drill core and samples, core photographs, and other

supporting data demonstrating that exploration was done in a fashion described in

the documentation of Placer Dome Inc’s (PDI) work. Based on the previous

operator’s descriptions, exploration and sampling procedures conform to or exceed

industry standards. Nevertheless, Crystallex drilled 2,188 m in twelve diamond drill

holes, for a total of 1,087 core samples, to verify the presence and tenor of

mineralization. In addition, 275 quality assurance/quality control (QA/QC) samples

were analyzed. The Crystallex drill results and check samples corroborate the

general tenor of gold mineralization reported by the previous operator. For additional

confirmation, Crystallex re-assayed 262 pre-existing pulps, 200 pre-existing coarse

rejects and 342 pre-existing quarter core samples. Mean grades are similar for both

datasets.

1.3.2 Resources

MDA completed a resource model that incorporated geology and analytical data.

The model contains estimates of gold, copper, cyanide soluble copper, silver, rock

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

7

type, rock density and metallurgical type. The estimation process began with the

creation of cross sections and interpretation of the geology. Once the geologic

model was defined, mineral domains for gold and copper were identified and

modeled. All of this data was refined on level plans and used to code the block

model.

There are seven material/rock types defined in the Las Cristinas model, listed from

the deepest to the surface: carbonate-stable bedrock (CSB), carbonate-leached

bedrock (CLB), saprock, sulfide saprolite (SAPS), mixed sulfide and oxide saprolite,

oxide saprolite (SAPO), and overburden. Gold was modeled in three mineral

domains (“unmineralized”, low-grade and higher-grade) across all material types

except overburden. Copper was modeled in four separate geologic domains: a)

bedrock and saprock (a thin veneer of partially saprolitized rock lying on top of the

bedrock); b) saprolite sulfide and mixed saprolite zones; c) oxide saprolite; and d)

overburden. For Mesones/Sofia, the bedrock copper was also modeled in three

copper domains. Silver was modeled without domains across all material types

except for overburden, which was estimated separately. A summary of the total gold

resources, following National Instrument 43-101 classifications, is given in Table 1-2.

Table 0-2 Las Cristinas Mineral Resources (Including Reserves)

Total Measured and Indicated

Cutoff Tonnes Gold Gold

(g Au/t) (g/t) Ounces

0.5 438,931,000 1.09 15,328,000

0.6 354,171,000 1.22 13,841,000

1.0 169,467,000 1.72 9,354,000

Total Inferred

Cutoff Tonnes Gold Gold

(g Au/t) (g/t) Ounces

0.5 207,889,000 0.91 6,064,000

0.6 144,999,000 1.07 4,966,000

1.0 47,726,000 1.76 2,703,000

*Note (1) Mineral Resources include mineral reserves

(2) Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability.

For comparison, the last resource estimate reported by Placer, at a cutoff of 0.6 g

Au/t, totaled 448,857,000 tonnes grading 1.19 g Au/t, for a total of 17,200,000

ounces of gold, which compares to the MDA total of 499,000,000 tonnes grading

1.17 g Au/t for a total of 18,807,000 ounces of gold (Measured, Indicated and

Inferred; reported together for comparison purposes only). MDA’s estimated

resource is larger presumably because Placer’s reported resource is that material

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

8

contained within the limits of an “optimistic” pit, whereas the MDA resource is not

limited.

1.3.3 Interpretations and Conclusions

Las Cristinas contains a gold deposit that is unique in terms of its geologic

characteristics and size. The geometry and size of the deposit give the project

operational flexibility that will allow optimal exploitation. The deposit is open ended at

depth and, with increased metal prices, decreased costs, and/or increased

metallurgical recoveries, reserves could increase. Additional drilling may result in

upgrading some or all of the Inferred resources to Measured or Indicated, which

could add to reserves.

As in all projects, there are certain aspects of the project and resource estimate that

can use additional study. The following recommendations regarding the geology and

resources are given not to show deficiencies, but rather to provide a higher level of

understanding of the project.

Additional drilling should be done which may upgrade resources from Inferred to

Measured and Indicated which could potentially increase reserves. Given the same

economic, mining, and engineering criteria, it is likely that the reserves can be

increased at depth but potentially also at Potaso where drilling could not be done in

an area of historic mining.

In a future stage there will be a heterogeneity study carried out to optimize sampling

protocol and minimize sample variance.

1.4 Reserves and Mining

The Las Cristinas deposit is planned to be mined as a conventional truck/shovel

operation. The bedrock will be mined by Crystallex using hydraulic excavators and

standard-rear-wheel-drive-haul trucks while the saprolite material will be mined by a

contractor using a different equipment fleet more suited to the material

characteristics. This strategy is based on Crystallex experience in similar conditions

in Venezuela.

Deposit reserves were developed by MDA from the MDA resource model using the

Canadian Institute of Mining, Metallurgy and Petroleum reserve definitions. The

reserves are summarized in Table 1-3.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

9

Table 0-3 Las Cristinas Reserves

Category Ore Grade Contained Waste Strip

Deposit

(applies to ore only)

kt (Au g/t)

Au oz

x1000 kt Ratio

PROVEN 36,620 1.38 1,625

Bedrock 26,147 1.37 1,150

Total 296,962

Saprolite 10,473 1.41 475 Bedrock 240,433

PROBABLE 187,117 1.27 7,669

Saprolite 56,529

Bedrock 144,358 1.30 6,025

Conductora

Saprolite 42,759 1.20 1,644

1.33:1

PROBABLE 21,922 1.24 871 Total 31,537

Mesones/Sophia

Bedrock 12,754 1.32 543 Bedrock 15,286

Saprolite 9,168 1.11 328 Saprolite 16,251

1.44:1

PROVEN 36,620 1.38 1,625

Bedrock 26,147 1.37 1,150

Total 328,499

Saprolite 10,473 1.41 475 Bedrock 255,719

PROBABLE 209,039 1.27 8,540

Saprolite 72,780

Bedrock 157,112 1.30 6,567

Total

Saprolite 51,927 1.18 1,973

1.34:1

PROVEN &

PROBABLE 245,659 1.29 10,165 Total 328,499

Total

Bedrock 183,259 1.31 7,717 Bedrock 255,719

Saprolite 62,400 1.22 2,447 Saprolite 72,780

1.34:1

Parameters used to develop the reserves, define cutoffs and develop pit designs are

summarized in Tables 1-4 and 1.5.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

10

Table 0-4 Pit Design Parameters

Description Value

CSB Gold plant recovery 87.6%

CLB Gold plant recovery 87.6%

SAPO Gold plant recovery 98.0%

SAPS Gold plant recovery 86.8%

Specific gravity (varies by rock type) 1.56-2.79

Saprolite bench height (double benched 12m) 6m

Bedrock bench height 12m

Road width 25m

Maximum road grade saprolite 8%

Maximum road grade bedrock 10%

Overall slope angle in saprolite 35°

Overall slope angle in CLB 45°

Overall slope angle in CSB east wall 45°

Overall slope angle in CSB west wall 50°+

Slope angle south wall all rocks 25°

Overall slope angle in deep saprolite >70 m 30°

Table 0-5 Economic Parameters

Value Description Units (US$)

$325 Gold price $/oz

$1.00 Cost of mining bedrock $/DMT

1

$1.17 Cost of mining saprolite $/DMT

1

$0.31 General and Administration $/DMT

1

ore

$3.81 Cost of milling-processing CSB $/DMT

1

ore

$3.11 Cost of milling-processing CLB $/DMT

1

ore

$2.11 Cost of milling-processing SAPO

2 $/DMT1

ore

$4.44 Avg Cost of milling-processing SAPS

2 $/DMT1

ore

(saps cost=2.487+0.0024235*CNSCu)

2204.62 Pounds per tonne conversion lb/tonne

31.1035 Grams per oz conversion g/oz

99.8% Gold payable in dore oxide %

$1.50 Gold refining oxide $/oz

CVG Royalty on gold

1.0% If gold is <= $280/oz %

1.5% If gold is < $350/oz and > $280/oz %

2.0% If gold is < $400/oz and >= $350/oz %

3.0% If gold is >= $400/oz %

3.0% Venezuelan Exploitation Tax %

1

DMT = Dry Metric Tonne

2

Saprolite processing cost includes $0.24/t for ore control

MDA used Medsystem-MineSight computer software to develop and report the

reserves. The general procedure was to generate a suite of ultimate pit shells for a

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

11

range of gold prices using the Medsystem Lerchs-Grossmann program. A specific pit

shell, based on the $325 gold price was chosen as a template for the final pit design.

The final design includes haul ramps and excludes areas that cannot be mined. (The

Lerchs-Grossmann program does not produce a designed pit.) Two separate pits

were designed, the larger Conductora, which contains the bulk of the reserves and

the Mesones/Sofia (referred to as Mesones). The Conductora pit was divided into

five phases or pushbacks to improve project economics and delay waste mining as

much as possible.

The pit slope angles were reviewed by Brawner Engineering Ltd (Vancouver B.C.,

Canada) which confirmed their appropriateness.

Waste dumps which follow were designed using Placer Dome criteria, general

industry standards. Because there is the potential for some of the mined waste to be

acid generating, this material will be encapsulated within the largest of the dumps

and surrounded by acid neutralizing materials. Placer Dome estimated that

approximately 31 million tonnes of saprolite sulfide and carbonate-leached bedrock

waste need encapsulation.

The final pit and dump designs are shown in Figure 1-1.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

12

Figure 1-1

Pit and Dump Designs

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

13

Because the region experiences considerable rainfall, over three metres per year on

average, water will be a major factor in mining. Groundwater flows from Placer

Dome documents were used to determine the amount of inflow expected in the pits.

Measured rainfall from a weather station on the site was used for the surface water

flows. SRK Consultants of Santiago Chile reviewed the available documentation and

developed anticipated inflows using computer modeling techniques.

The mine production schedule developed by MDA is based on providing the plant

with 20,000 tonnes of ore per day, or 7.3 million ore tonnes per year. This schedule

results in a mine life of just under 34 years. Waste to ore stripping ratios range from

0.21:1 in the second quarter of the first production year to a maximum of 3.0:1 in year

28. Saprolite oxide ore is accessible on the surface from startup. During the preproduction

period 7.0 million tonnes of saprolite are mined, 5.5 million of which are

ore and are stockpiled until bedrock ore is available. The production schedule is

shown in Table 1-6.

The cut-offs range from 0.37 g/t to 0.69 g/t depending on material type.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

14

Table 0-6 Production Schedule

Y e a r P r e P r o d u c t i o n Q 1 Q 2 Q 3 Q 4 1 2 3 4 5 6 - 1 0 1 1 - 1 5 1 6 - 2 0 2 1 - 2 5

M i l l T h r o u g h p u t ( k t )

1 , 8 2 5 1 , 8 2 5 1 , 8 2 5 1 , 8 2 5 7 , 3 0 0 7 , 3 0 0 7 , 3 0 0 7 , 3 0 0 7 , 3 0 0 3 6 , 5 0 0 3 6 , 5 0 0 3 6 , 5 0 0 3 6 , 5 0 0

C o n t a in e d G o ld , k g 2 , 7 4 7 2 , 5 4 6 2 , 9 5 7 2 , 7 5 5 1 1 , 0 0 5 1 0 , 6 2 9 1 0 , 1 2 5 1 0 , 5 4 4 1 0 , 4 7 7 4 3 , 0 0 4 4 4 , 5 9 1 4 9 , 1 8 3 4 3 , 9 3 5

C o n t a in e d G o ld , o z ( 0 0 0 's ) 8 8 8 2 9 5 8 9 3 5 4 3 4 2 3 2 6 3 3 9 3 3 7 1 , 3 8 3 1 , 4 3 4 1 , 5 8 1 1 , 4 1 3

A u ( g / t ) 1 . 5 1 1 . 4 0 1 . 6 2 1 . 5 1 1 . 5 1 1 . 4 6 1 . 3 9 1 . 4 4 1 . 4 4 1 . 1 8 1 . 2 2 1 . 3 5 1 . 2 0

G o ld R e c o v e r y ( % ) 9 4 . 0 % 9 3 . 5 % 9 3 . 9 % 9 3 .2 % 9 3 . 7 % 9 1 .9 % 9 1 . 2 % 9 0 .7 % 9 0 . 3 % 8 9 . 9 % 8 8 . 7 % 8 8 .5 % 8 8 . 2 %

R e c o v e r e d G o ld , k g 2 , 5 8 2 2 , 3 8 0 2 , 7 7 6 2 , 5 6 8 1 0 , 3 0 7 9 , 7 7 0 9 , 2 3 5 9 , 5 6 6 9 , 4 6 2 3 8 , 6 7 8 3 9 , 5 6 2 4 3 , 5 3 6 3 8 , 7 4 7

R e c o v e r e d G o ld , o z ( 0 0 0 's ) 8 3 7 7 8 9 8 3 3 3 1 3 1 4 2 9 7 3 0 8 3 0 4 1 2 4 4 1 2 7 2 1 4 0 0 1 2 4 6

S a p r o l i t e O x id e ( k t )

9 1 3 9 1 3 9 1 3 9 1 2 3 , 6 5 1 3 , 1 3 9 3 , 1 3 9 3 , 1 3 9 3 , 1 3 9 9 , 4 1 7 5 , 2 9 5 4 , 7 4 5 2 , 9 2 0

P e r c e n t a g e o f T o t a l 5 0 . 0 % 5 0 . 0 % 5 0 . 0 % 5 0 .0 % 5 0 . 0 % 4 3 .0 % 4 3 . 0 % 4 3 .0 % 4 3 . 0 % 2 5 . 8 % 1 4 . 5 % 1 3 .0 % 8 .0 %

A u ( g / t ) 1 . 8 5 1 . 5 8 1 . 9 6 1 . 6 3 1 . 7 6 1 . 4 3 1 . 1 4 1 . 0 3 0 . 8 9 1 . 0 6 0 . 9 8 0 . 9 9 0 . 9 8

C o n t a in e d G o ld , k g 1 6 8 9 1 4 4 3 1 7 8 9 1 4 8 7 6 4 0 8 4 4 8 9 3 5 8 2 3 2 3 4 2 7 9 4 9 9 4 4 5 2 0 5 4 7 1 6 2 8 4 7

C o n t a in e d G o ld , o z ( 0 0 0 's ) 5 4 4 6 5 8 4 8 2 0 6 1 4 4 1 1 5 1 0 4 9 0 3 2 0 1 6 7 1 5 2 9 2

G o ld R e c o v e r y ( % ) 9 8 . 0 % 9 8 . 0 % 9 8 . 0 % 9 8 .0 % 9 8 . 0 % 9 8 .0 % 9 8 . 0 % 9 8 .0 % 9 8 . 0 % 9 8 . 0 % 9 8 . 0 % 9 8 .0 % 9 8 . 0 %

R e c o v e r e d G o ld , k g 1 , 6 5 5 1 , 4 1 4 1 , 7 5 4 1 , 4 5 7 6 , 2 7 9 4 , 3 9 9 3 , 5 1 1 3 , 1 6 9 2 , 7 3 8 9 , 7 4 5 5 , 1 0 1 4 , 6 2 1 2 , 7 9 0

R e c o v e r e d G o ld , o z ( 0 0 0 's ) 5 3 4 5 5 6 4 7 2 0 2 1 4 1 1 1 3 1 0 2 8 8 3 1 3 1 6 4 1 4 9 9 0

S a p r o l i t e S u l p h i d e ( k t )

0 0 0 0 0 5 1 1 5 1 1 5 1 1 5 1 1 2 , 5 5 5 3 , 6 5 0 3 , 6 5 0 3 , 6 5 0

P e r c e n t a g e o f T o t a l 0 . 0 % 0 . 0 % 0 . 0 % 0 .0 % 0 .0 % 7 .0 % 7 .0 % 7 . 0 % 7 . 0 % 7 . 0 % 1 0 . 0 % 1 0 .0 % 1 0 . 0 %

A u ( g / t ) 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 . 7 8 1 . 7 8 1 . 7 6 1 . 3 8 1 . 3 7 1 . 4 0 1 . 3 3 1 . 2 5

C o n t a in e d G o ld , k g 0 0 0 0 0 9 1 2 9 1 1 9 0 0 7 0 3 3 5 0 7 5 1 0 8 4 8 6 3 4 5 4 8

C o n t a in e d G o ld , o z ( 0 0 0 's ) 0 0 0 0 0 2 9 2 9 2 9 2 3 1 1 3 1 6 4 1 5 6 1 4 6

G o ld R e c o v e r y ( % ) 8 6 . 8 % 8 6 . 8 % 8 6 . 8 % 8 6 .8 % 8 6 . 8 % 8 6 .8 % 8 6 . 8 % 8 6 .8 % 8 6 . 8 % 8 6 . 8 % 8 6 . 8 % 8 6 .8 % 8 6 . 8 %

R e c o v e r e d G o ld , k g 0 0 0 0 0 7 9 2 7 9 1 7 8 1 6 1 1 3 , 0 4 4 4 , 4 3 4 4 , 2 2 2 3 , 9 4 8

R e c o v e r e d G o ld , o z ( 0 0 0 's ) 0 0 0 0 0 2 5 2 5 2 5 2 0 9 8 1 4 3 1 3 6 1 2 7

C a r b o n a t e L e a c h B e d r o c k ( k t )

9 1 2 9 1 2 9 1 2 9 1 2 3 , 6 4 8 3 , 3 6 4 2 , 4 9 0 1 , 0 2 4 5 3 6 1 6 , 0 3 6 6 , 4 3 5 1 , 1 9 9 1 2 , 8 9 2

P e r c e n t a g e o f T o t a l 5 0 . 0 % 5 0 . 0 % 5 0 . 0 % 5 0 .0 % 5 0 . 0 % 4 6 .1 % 3 4 . 1 % 1 4 .0 % 7 . 3 % 4 3 . 9 % 1 7 . 6 % 3 .3 % 3 5 . 3 %

A u ( g / t ) 1 . 1 6 1 . 2 1 1 . 2 8 1 . 3 9 1 . 2 6 1 . 4 3 1 . 4 7 1 . 4 9 1 . 4 6 1 . 1 9 1 . 2 1 0 . 9 8 1 . 0 4

C o n t a in e d G o ld , k g 1 0 5 8 1 1 0 4 1 1 6 7 1 2 6 8 4 5 9 6 4 8 1 1 3 6 6 0 1 5 2 6 7 8 3 1 9 0 6 9 7 7 6 1 1 1 7 1 1 3 4 7 0

C o n t a in e d G o ld , o z ( 0 0 0 's ) 3 4 3 5 3 8 4 1 1 4 8 1 5 5 1 1 8 4 9 2 5 6 1 3 2 5 0 3 8 4 3 3

G o ld R e c o v e r y ( % ) 8 7 . 6 % 8 7 . 6 % 8 7 . 6 % 8 7 .6 % 8 7 . 6 % 8 7 .6 % 8 7 . 6 % 8 7 .6 % 8 7 . 6 % 8 7 . 6 % 8 7 . 6 % 8 7 .6 % 8 7 . 6 %

R e c o v e r e d G o ld , k g 9 2 7 9 6 7 1 , 0 2 3 1 , 1 1 0 4 , 0 2 7 4 , 2 1 4 3 , 2 0 6 1 , 3 3 7 6 8 6 1 6 , 7 0 5 6 , 7 9 9 1 , 0 2 6 1 1 , 8 0 0

R e c o v e r e d G o ld , o z ( 0 0 0 's ) 3 0 3 1 3 3 3 6 1 2 9 1 3 5 1 0 3 4 3 2 2 5 3 7 2 1 9 3 3 3 7 9

C a r b o n a t e S t a b l e B e d r o c k ( k t )

0 0 0 1 1 2 8 6 1 , 1 6 0 2 , 6 2 6 3 , 1 1 4 8 , 4 9 2 2 1 , 1 2 0 2 6 , 9 0 6 1 7 , 0 3 8

P e r c e n t a g e o f T o t a l 0 .0 % 0 .0 % 0 .0 % 0 . 1 % 0 . 0 % 3 . 9 % 1 5 . 9 % 3 6 . 0 % 4 2 . 7 % 2 3 .3 % 5 7 . 9 % 7 3 . 7 % 4 6 . 7 %

A u ( g / t ) 0 . 0 0 0 . 0 0 0 . 0 0 0 . 8 3 0 . 8 3 1 . 4 6 1 . 7 0 1 . 8 6 1 . 9 9 1 . 2 3 1 . 2 6 1 . 4 3 1 . 3 5

C o n t a in e d G o ld , k g 0 0 0 1 1 4 1 8 1 9 7 2 4 8 8 4 6 1 9 7 1 0 4 8 4 2 6 5 1 7 3 8 4 3 3 2 3 0 7 1

C o n t a in e d G o ld , o z ( 0 0 0 's ) 0 0 0 0 0 1 3 6 3 1 5 7 1 9 9 3 3 7 8 5 3 1 2 3 6 7 4 2

G o ld R e c o v e r y ( % ) 8 7 . 6 % 8 7 . 6 % 8 7 . 6 % 8 7 .6 % 8 7 . 6 % 8 7 .6 % 8 7 . 6 % 8 7 .6 % 8 7 . 6 % 8 7 . 6 % 8 7 . 6 % 8 7 .6 % 8 7 . 6 %

R e c o v e r e d G o ld , k g 0 0 0 1 1 3 6 6 1 , 7 2 7 4 , 2 7 9 5 , 4 2 8 9 , 1 8 4 2 3 , 2 2 9 3 3 , 6 6 7 2 0 , 2 1 0

R e c o v e r e d G o ld , o z ( 0 0 0 's ) 0 0 0 0 0 1 2 5 6 1 3 8 1 7 5 2 9 5 7 4 7 1 0 8 2 6 5 0

W A S T E

P r e P r o d u c t i o n Q 1 Q 2 Q 3 Q 4 1 2 3 4 5 6 - 1 0 1 1 - 1 5 1 6 - 2 0 2 1 - 2 5

S a p r o l i t e O x id e ( k t )

1 , 2 0 8 7 4 2 2 1 2 8 5 0 8 7 3 2 1 , 9 3 8 2 , 6 9 6 3 , 0 3 8 2 , 2 9 5 1 0 , 7 4 8 1 0 , 1 6 6 9 , 1 2 9 5 1 4

S a p r o l i t e S u l p h i d e ( k t )

1 0 1 2 6 8 2 7 7 4 0 3 6 9 2 0 0 4 2 1 , 9 5 1 6 , 3 9 7 1 , 4 3 5 9 , 7 6 9 7 , 6 7 2

C a r b o n a t e L e a c h B e d r o c k ( k t )

0 7 0 9 5 6 3 4 3 9 3 8 8 2 , 0 9 9 1 , 2 8 5 6 7 0 1 , 1 7 8 1 , 3 1 6 1 9 , 0 9 6 6 , 1 6 9 3 , 0 5 2 2 3 , 8 5 6

C a r b o n a t e S t a b l e B e d r o c k ( k t )

0 0 0 1 5 6 1 6 4 4 5 2 5 1 2 1 0 1 9 , 3 5 0 3 2 , 0 8 2 1 7 , 1 8 8 1 9 , 5 0 4

T O T A L

1 , 3 0 9 1 , 0 5 1 6 1 2 6 4 2 9 0 1 3 , 2 0 6 3 , 4 0 7 3 , 8 1 8 4 , 7 7 0 5 , 6 6 3 4 5 , 5 9 1 4 9 , 8 5 2 3 9 , 1 3 8 5 1 , 5 4 6

T O S T O C K P I L E

P r e P r o d u c t i o n Q 1 Q 2 Q 3 Q 4 1 2 3 4 5 6 - 1 0 1 1 - 1 5 1 6 - 2 0 2 1 - 2 5

S a p r o l i t e O x id e ( k t )

4 , 6 7 9 0 3 7 6 0 7 0 6 1 , 0 8 2 1 4 0 0 0 0 5 , 6 6 5 0 2 , 3 9 9 0

S a p r o l i t e S u l p h i d e ( k t )

8 4 3 2 , 3 3 0 7 4 6 8 0 8 1 2 8 4 , 0 1 2 0 0 0 7 0 3 6 , 0 4 1 0 1 , 5 4 0 4 1 4

T O T A L

5 , 5 2 2 2 , 3 3 0 1 , 1 2 2 8 0 8 8 3 4 5 , 0 9 4 1 4 0 0 0 7 0 3 1 1 , 7 0 6 0 3 , 9 3 9 4 1 4

F R O M S T O C K P IL E

P r e P r o d u c t i o n Q 1 Q 2 Q 3 Q 4 1 2 3 4 5 6 - 1 0 1 1 - 1 5 1 6 - 2 0 2 1 - 2 5

S a p r o l i t e O x id e ( k t )

0 6 4 9 0 1 4 0 0 7 8 9 0 2 3 3 1 , 0 8 2 3 , 9 0 4 3 , 4 5 2 1 , 6 6 4 2 , 7 6 6

S a p r o l i t e S u l p h i d e ( k t )

0 0 0 0 0 0 2 6 1 5 1 0 4 8 1 0 0 2 , 6 8 8 1 , 5 5 7 1 , 5 4 1

T O T A L

0 6 4 9 0 1 4 0 0 7 8 9 2 6 1 5 3 3 4 8 4 1 , 0 8 2 3 , 9 0 4 6 , 1 4 0 3 , 2 2 1 4 , 3 0 7

S T O C K P IL E V O L U M E S

P r e P r o d u c t i o n Q 1 Q 2 Q 3 Q 4 1 2 3 4 5 6 - 1 0 1 1 - 1 5 1 6 - 2 0 2 1 - 2 5

( e n d o f p e r io d )

S a p r o l i t e O x id e ( k t )

4 , 6 7 9 4 , 0 3 0 4 , 4 0 6 4 , 2 6 6 4 , 9 7 2 4 , 9 7 2 5 , 1 1 2 5 , 0 8 9 5 , 0 8 6 4 , 0 0 4 5 , 7 6 5 2 , 3 1 3 3 , 0 4 8 2 8 2

S a p r o l i t e S u l p h i d e ( k t )

8 4 3 3 , 1 7 3 3 , 9 1 9 4 , 7 2 7 4 , 8 5 5 4 , 8 5 5 4 , 5 9 4 4 , 0 8 4 3 , 6 0 3 4 , 3 0 6 1 0 , 3 4 7 7 , 6 5 9 7 , 6 4 2 6 , 5 1 5

T O T A L

5 , 5 2 2 7 , 2 0 3 8 , 3 2 5 8 , 9 9 3 9 , 8 2 7 9 , 8 2 7 9 , 7 0 6 9 , 1 7 3 8 , 6 8 9 8 , 3 1 0 1 6 , 1 1 2 9 , 9 7 2 1 0 , 6 9 0 6 , 7 9 7

P r o d u c t i o n S c h e d u l i n g b y P e r io d

Stockpiling of saprolite ore is necessary to maintain the desired blend of saprolite

and bedrock plant feed. The majority of the saprolite is mined in the first half of the

mine life because the saprolite overlies the bedrock and therefore must be mined

before the bedrock can be accessed. Saprolite oxide is restricted to a maximum of

50% of the plant feed in year 1, or 10,000 tonnes per day and 43% per year

thereafter. Bedrock ore cannot exceed 75% of the plant feed without a drop in

production rates. The bedrock limit was relaxed after year 20 to 80% and allowed to

reach 90% after year 25. This was done to reduce the size of the saprolite ore

stockpiles, which would otherwise become costly.

Additionally, saprolite sulfide material cannot exceed 7% of the total plant feed during

the first 10 years and cannot exceed 10% after that. This restriction is relaxed in the

last two years of life. The increase in the proportion of sulfide feed to the plant is a

compromise between plant operations and ore stockpile management. A separate

stockpile is maintained for the saprolite sulfide.

The maximum size of the saprolite ore stockpiles is just under 16.5 million tonnes.

Over the life of the mine a total of approximately 28 million tonnes of saprolite ore is

stockpiled. Re-handling the stockpiled ore will be a challenge given the material

characteristics and the amount of rainfall at the site.

The saprolite oxide stockpile is divided into two areas, a high-grade area and a lowgrade

area. This is done to increase the feed grade in the early years by sending the

high-grade material to the plant first, thus increasing the recovered gold ounces and

improving the overall project economics. After year 10 the distinction between high

and low grades was discontinued. The average gold grade in the high-grade

stockpile is 2.0 g Au/t and the gold grade in the low-grade stockpile is 0.76 g Au/t.

MDA divided only the oxide in this way but the sulfide material could be handled in a

similar manner, although the benefit of this is limited by the restriction on the amount

of sulfide material in the plant feed.

Different mining equipment is used in the saprolite and bedrock due to the

significantly different material characteristics. A contractor will mine the saprolite

using a fleet of all-wheel-drive trucks and excavators. Crystallex will mine the

bedrock using conventional 136 tonne haul trucks and 21m

3

capacity excavator and

loader. The bedrock requires drilling and blasting while the saprolite does not. The

number of trucks in the bedrock mining fleet averages 6 over the life of the mine with

a maximum of 15 during years 27 through 29. Appropriate support equipment is

planned to maintain the site roads and access roads as well as the pit and dumps.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

16

Mine manpower requirements vary with production levels but start at a base level of

94 people. This figure includes 15 in mine engineering and geology, 27 in mine

maintenance and 52 in mine operations. The maximum manpower level is 217

during years 27 through 29. The mine operations manager, chief mine engineer and

maintenance superintendent are initially expatriates and are replaced by Venezuelan

nationals after the second operating year.

The life-of-mine mine operating cost is estimated to be $2.94 per tonne of total ore or

$1.26 per total mined tonne, including saprolite mining. Pre-production contract

mining ($9.6 million) is considered a capital cost and not included in operating costs.

Total bedrock mining costs without the contract saprolite mining amount to $0.95 per

mined tonne or $2.23 per ore tonne.

Costs for major consumables and labour are primarily based on prices reported by

Crystallex from its current Venezuelan operations and independent budget

quotations. Fuel prices are low in Venezuela, $0.04 per litre is used for this work.

Contract saprolite mining is $1.37 per dry tonne based on budgetary bids from

contract mining firms currently working in Venezuela.

Currently in Venezuela the prices for explosives are established by a non-competitive

market and consequently are higher than prices in most other South American

countries. The costs used in this study of $1830/tonne for emulsion and $1000/tonne

for ANFO are based on the actual prices paid by Crystallex at their existing

operations and averages of other quotes received by MDA and Crystallex. Crystallex

currently pays $1200/tonne for ANFO at a Venezuelan mine much smaller than Las

Cristinas.

1.5 Metallurgy

SGS Lakefield Research (Lakefield) conducted an extensive program to test samples

of saprolite oxide (SAPO), saprolite sulphide (SAPS), carbonate leached bedrock

(CLB) and carbonate stable bedrock (CSB) in bench tests and a 50 kg/day pilot plant

operation, run for 21 days during the months of April through July 2003 . Subsamples

were sent to McGill University for gravity recovery testwork. Outokumpu

conducted pilot plant settling tests on several samples. The various test programs

were designed to confirm relevant data generated by PDI, determine the gold

recovery and reagent requirements for the proposed gravity-leach flowsheet, and

generate plant design data.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

17

Grinding data from Lakefield are generally in accordance with data generated by

Placer Dome. Pilot scale gravity concentration tests at Lakefield show about 30%

gold recovery from both a SAPO-CSB blend and a SAPO-SAPS-CLB-CSB blend at

mass concentration ratios of about 4000:1. Intensive cyanidation of the concentrates

from these tests gave >99% leach recovery. Tests at McGill to determine the gravity

recoverable gold (GRG) content of SAPO and CSB samples showed 39% and 46%

GRG, respectively which would translate into practical recoveries of about 25%

Thirty-six hour bottle roll leach tests (an industry standard) on gravity tailings confirm

that SAPO leaches very well to give about 99% overall (gravity+leaching) extraction

and a 0.02 g/t tailing. With a 24 h leach time, tailings were 0.03 g/t corresponding to

98% extraction. CSB gives about 85% overall extraction (0.17 g/t tailing). Cyanide

additions for SAPO and CSB have been less than 1 kg/t ore. Pure SAPS samples

with cyanide soluble copper (CNSCu) levels of 370 ppm or less have been tested

and gave 85 to 88% extraction, albeit with cyanide additions of 1.7 to 1.9 kg/t.

Mixtures containing SAPO, SAPS and CSB gave 85 to 90% overall extraction

provided that sufficient NaCN was present. The NaCN addition varied with the

CNSCu level in the ore.

A 2 kg/h pilot plant was operated for three weeks in which batch-ground/gravity

concentrated ore was subjected to carbon-in-leach (CIL) processing. During the first

13 days, a blend of 20% SAPO and 80% CSB was leached with 0.7 kg/t of cyanide to

give a final overall gold extraction of 89.6% (tailings average of 0.15 g/t). A SAPOSAPS-

CLB-CSB blend was processed for the last week. The plant tailing was 0.15

g/t for an extraction of 89.3% with a cyanide addition of 0.8 kg/t. Overall gold

recovery used in the preliminary design was 89%.

Viscosity measurements by Lakefield were acceptable for the mixtures that will be

handled in the Las Cristinas plant.

Outokumpu conducted high-rate thickening tests on nine sample blends, ranging

from pure SAPO to pure bedrock, using its pilot-scale thickener. At 50% solids in the

underflow, all blends containing 50% SAPO or less could be processed at 0.46 t/m

2

/h

or greater. Allowing for a 15% scale-up, the data showed that a 50 m diameter

thickener would give at least 47% solids in the underflow when processing up to 20

000 t/d of a 50% SAPO, 50% CSB mixture.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

18

Acid-base-accounting (ABA) tests and various geotechnical studies were performed

by Lakefield on several samples to determine the potential for acid generation. Data

are discussed in Section 12 of this study report.

Natural degradation tests and continuous INCO Air/SO

2

cyanide destruction tests

have been performed on pilot plant tailings. Natural degradation under Lakefield

climatic conditions reduced CN

WAD

to below 20 ppm in about 40 d. The INCO

process then reduced CN

WAD

to 0.2 ppm and Cu to about 1 ppm under industrytypical

operating conditions. INCO tests will be performed on PP2 tailings solution in

the near future.

1.6 Processing

1.6.1 General

All equipment, with the exception of secure areas such as electrowinning and the

gold, electrical and control rooms, is located in open sided structures or outdoors.

The processing plant is fenced for gold security reasons. Installed spare pumps are

provided for all critical process streams.

The process plant consists of single line crushing, semi-autogenous primary grinding

(SAG) followed by secondary grinding using a ball mill. A pebble crusher is

incorporated in closed circuit with the SAG mill.

A gravity circuit is included in closed circuit with the cyclones in order to recover any

coarse, free gold prior to regrinding in the ball mill.

Gold extraction is achieved in a conventional carbon-in-leach (CIL) circuit. Gold is

removed from the loaded carbon by pressure stripping, electrowinning and smelting a

gold dore product.

1.6.2 Primary Crushing

CLB and CSB ore is delivered by mine truck to the primary crushing station which is

permanently located to the east of the process plant. The primary crusher product

discharges via an apron feeder on the stockpile feed conveyor.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

19

1.6.3 Ore Storage and Reclaim

CLB and CSB ore is reclaimed from the coarse ore stockpile using apron feeders

located in the reclaim tunnel situated below the stockpile. The ore is loaded onto the

SAG mill feed conveyor.

1.6.4 Saprolite Crushing

SAPO and SAPS ore is delivered by mine truck to the saprolite crushing station. The

mine trucks direct dump into a feed hopper which is positioned over top of an apron

feeder. The apron feeder passes the saprolite ore into a mineral sizer in order to

reduce over sized clumps before being fed on to the SAG mill feed conveyor.

1.6.5 Grinding

The SAG mill feed conveyor delivers a combination of saprolite, CLB and CSB ore

directly to the SAG mill. The SAG mill is driven by a clutch and pinion gear

arrangement by a variable speed synchronous motor. The SAG mill discharge is

screened by a double deck vibrating screen to remove over sized 12 mm pebbles.

The 12 mm pebbles from the vibrating screen are crushed in a cone crusher prior to

being recycled back to the SAG mill feed chute. Provision has also been made so

the pebbles can be recycled directly back to the SAG mill without further size

reduction or can be stockpiled outside the process plant building.

The under sized product from the vibrating screen drops into the cyclone feed pump

box where it is combined with the discharge from the ball mill. The ball mill is driven

by a wrap around, variable speed motor through a cycloconverter drive unit.

The combined SAG and ball mill discharges are diluted in the pump box with process

water and pumped to a cyclone cluster which sorts the ore particles by size and

returns the over size to the ball mill for further size reduction.

Also included in the grinding circuit is a gravity recovery circuit. A portion of the ball

mill discharge is diverted over a vibrating screen with the under size fed to one of two

centrifugal concentrators. Gravity concentrate from each centrifugal concentrator is

stored in a secured holding cone until it is leached in a semi-batch, high intensity

cyanide leach reactor. Gravity and leach reactor tailings are pumped backed to the

grinding circuit. The gold loaded solution from the leach reactor is pumped to a

dedicated electrowinning circuit located in the secured gold room.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

20

1.6.6 Carbon-in-Leach (CIL)

Slurry from the grinding circuit cylcone overflow, after trash removal, is gravity fed to

the thickener feed collection box where slurry flows into a 45 m diameter thickener.

The thickener overflow flows by gravity into the process water tank. The thickener

underflow is pumped at 50% solids by weight into dual parallel 6-stage CIL circuits.

Cyanide and lime are staged added to each tank train. On an intermittent basis,

loaded carbon is pumped counter current to the slurry flow in order to increase the

gold loading. Loaded carbon is removed from the head end of each tank train and is

transferred to the acid wash vessel via a vibrating screen.

1.6.7 Carbon Desorption and Regeneration

Loaded carbon captured by the vibrating screen drops by gravity into the acid wash

vessel. A 3% acid solution is pumped into the acid wash vessel and overflows the

top and returns to the acid mix tank. Acid washing takes approximately 1 hour. After

acid washing is complete, the spent acid is neutralized with sodium hydroxide before

discarding it to the tails pump box.

The desorption elution cycle starts with the preparation of a 3% sodium cyanide and

2% sodium hydroxide solution in the barren eluate tank. The solution is initially

pumped through the strip solution heater and returns to the barren eluate tank until

its temperature reaches 80

°

C. The solution is then directed through a recovery heat

exchanger, and through the strip solution heater to bring its temperature up to 145

°

C

before entering the elution column. Barren eluate solution at operating temperature

and 300 kPa pressure enters the bottom of the elution vessel through in-line screens

then flows up through the carbon bed. The solution desorbs the metal loaded onto

the carbon then exits from the top of the elution vessel and passes through a screen

basket to retain carbon. The new solution passes through the solution/solution heat

exchanger where it transfers its thermal energy to the incoming barren eluate

solution. The pregnant solution exits the hot side outlet of the heat recovery

exchanger at 65

°

C. This pregnant solution stream then flows to the pregnant elution

tank in the electrowinning and refining area.

Stripped carbon is evacuated from the bottom of the elution vessel and is transferred

to a vibrating screen at the top of the carbon regeneration kiln feed hopper. Carbon is

screened out and drops by gravity into the hopper. Screen fines flow by gravity to the

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

21

carbon fines tank. Water collected in the carbon fines tank is pumped through a plate

and frame filter press to capture any carbon fines.

The activity of the stripped carbon is restored in a kiln. After passing through the kiln,

the carbon drops out into a quench tank and is transported to the reactivated / fresh

carbon sizing screen. Screened carbon drops by gravity to the reactivated carbon

transfer hopper where it is mixed with washed fresh carbon. Screen fines flow by

gravity to the carbon fines tank. Water collected in the carbon fines tank is pumped

through a plate and frame filter press to capture any carbon fines.

There is some carbon loss through attrition and is made up with fresh carbon. Mixed

regenerated/fresh carbon in the transfer hopper is moved to the last leach tank in the

train via a horizontal recessed impeller pump.

1.6.8 Electrowinning and Refining

Pregnant eluate solution from the desorption operation reports to the pregnant eluate

tank. Pregnant eluate solution is pumped to four electrowinning cells (two rows of

two in parallel). Gold metal is electrowon loosely on the stainless steel wool

cathodes in the electrowinning cells. Depleted solution flows from the outlet of each

cell to the barren eluate return tank and is then transported either back to the barren

eluate tank or recirculated back through the electrowinning cells via the pregnant

eluate tank.

Pregnant eluate from the concentrate leach circuit is pumped to the leach reactor

pregnant eluate tank in the refinery area. Pregnant eluate solution is transported

from the tank to two electrowinning cells in series. Gold metal is electrowon loosely

on the stainless steel wool cathodes in the electrowinning cells. Depleted solution

flows from the outlet of the last cell to the leach reactor barren eluate return tank and

is then transported either to the CIL circuit or recirculated back through the

electrowinning cells via the leach reactor pregnant eluate tank.

At the end of the run, the cathodes are removed from the cells; the gold bearing

sludge is washed off and then pumped to a plate and frame filter press. The filter

cake is mixed with fluxes, usually borax, soda ash and occasionally sodium nitrate

and fed to an electric induction furnace. The doré metal and slag separate in the

furnace, and the slag is poured off to slag pots then the doré metal is poured into

bars for shipment.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

22

1.6.9 Cyanide Destruction

The cyanide destruction process is air/SO

2

using sodium metabisulphite as the

source of SO

2

. At present only reclaim water from the TMF will be treated however

provision for future treatment of CIL tailings has been made, if deemed necessary.

This will not have a significant economic impact on the project and current Crystallex

experience in Venezuela indicates that this will not be necessary. The cyanide

destruction tank is fitted with an agitator consisting of dual impellers supported from a

bridge mounted on the tank shell. Air is introduced through a bottom entering line to

an inverted cone under the centre shaft of the agitator. The air bubbles then travel

upward into the maximum shear zone of the impeller blades.

Sodium metabisulphite solution is added at a rate sufficient to reduce the free

cyanide to below detection limits along with the level of weak acid dissociable (WAD)

cyanide complexes in the tailings pond water. Provision is made to add lime slurry to

maintain pH between 8 and 8.5.

1.7 Infrastructure and Services

1.7.1 Site Access

The Las Cristinas site is situated in south eastern Venezuela and is some 6 km west

of the village of Las Claritas on Troncal 10 the main highway running from the

Brazilian border to the Venezuelan port of Puerto Ordaz on the Orinoco River. The

site is some 360 km by road from Puerto Ordaz and the road presents no significant

obstacles to the transportation of goods and materials to the site.

Access to the site will be from Troncal 10 along an existing unpaved road that will be

upgraded to take construction and operational traffic. This route is 19 km long and

being north of Las Claritas circumnavigates all the local villages and will thus avoid

any disruptions to the local population.

1.7.2 Power Supply

An existing 400 kV power line parallels Troncal 10 and a new substation was

constructed in 2001 just south of Las Claritas at Km 86 to service the area. The

substation has two 150 MVA power transformers and provision has been built in to

supply Las Cristinas with a 230 kV power line.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

23

The site power demand is estimated at 30 MW which can be adequately supplied by

the substation.

Power to the site will be carried via a new overhead power line, a distance of

approximately 6 km, and will terminate at a new substation to be built on site from

where power will be distributed at 6.6 kV.

1.7.3 Site Water Supply

Potable water will be drawn from on-site wells and will be chlorinated prior to

distribution for consumption. Make-up water for process requirements will be drawn

from the Potaso Pit, an old mining pit that is permanently flooded. During operations

the Potaso pit will be charged with water from the diversion ditch.

1.7.4 Sewage Treatment

Domestic sewage will be collected by a system of gravity sewers and treated

biologically with the resulting effluent being pumped to the tailings pond.

1.7.5 Existing Facilities

In 1998 a 3,058 person construction camp was constructed at the Las Cristinas

property. The camp included dormitories for workers and supervisors, kitchen and

canteen facilities, administration building, water and firewater plant and a sewage

treatment plant. The camp was subsequently abandoned and has been subject to

neglect and minor vandalism.

For the current project the construction camp will not be utilized except that the

administration building will be refurbished and will serve as the main administration

centre, the kitchen and canteen will be converted to a construction and operations

warehouse and the existing water plant will be brought on line. Sewage from the

camp site will be redirected to the new sewage treatment plant.

1.7.6 Ancillary Buildings

Aside from the main administration facilities located in the existing construction camp

additional buildings will include a Guard House at the entrance to the process plant

area, a Mill Administration and Dry, a Truck Maintenance and Mine Dry and a Truck

Wash.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

24

1.7.7 Site Water Management Scheme and Water Balance

Tailings area water management forms a large component of overall site water

management. Therefore the tailings area water balance was developed in

combination with the overall site water balance to support the development of the site

water management scheme. The water balance provides an indication of average

process water flow rates, range of tailings pond operating volumes, average

treatment rates for water treatment plants, average pumping rates from water

management ponds and average discharge rates of excess water to the

environment.

The site water management scheme has been developed so that pumping and

treatment costs are minimized by isolating clean runoff from potentially contaminated

runoff and process water streams. Environmental impact is reduced by providing

appropriate containment and treatment to all potentially contaminated site water

before discharge, and by maximizing the use of water recycling.

Six site water management ponds are proposed in addition to the tailings pond. All

runoff from waste rock dumps and saprolite waste dumps will be collected in ponds

to provide settling of suspended solids. All runoff from waste rock dumps will be

monitored for acid drainage.

Process reclaim water from the Tailings Management Facility (TMF) water reclaim

system will pass through a cyanide destruction facility before use in the process

plant. Freshwater makeup will be supplied by pumping from the Potaso Pit. This

water will require treatment in a sedimentation/filtration plant before entering the

process stream. Any seepage from the TMF dike will be collected by a perimeter

ditch and pumped back. Excess TMF pond water will be considered suitable for

discharge to the environment following cyanide removal if suspended solids are

within an acceptable range.

Clean surface water from upstream drainage areas will be collected into a diversion

channel and conveyed around the perimeter of the site. Clean surface runoff from

undisturbed drainage areas within the mine site will be collected and diverted to the

Potaso Pit which overflows into the river diversion system. Site drainage was

designed for a 1:25 year flood event and the river diversions for 1:100 year events.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

25

1.8 Tailings Management Facilities

1.8.1 Field Investigations

A field program for the Tailings Pond area was undertaken by Bruce Geotechnical

Consultants Inc. (BGC), in 1994 and 1995 and reported in the Las Cristinas

Feasibility Study (BGC, 1996). BGC drilled 9 boreholes, dug 27 test pits and carried

out geologic mapping of outcrops. The geologic horizons were described as follows.

The upper horizon consists of a thin laterite soil horizon from 0.5 to 1.0 m thick. The

next two units are saprolite which will form the foundation immediately beneath the

tailings dikes. The upper layer of saprolite oxide (SAPO) is from 0 to 40 m in

thickness, while the thickness of the underlying layer of sulphide stable saprolite

(SAPS) varies from 0 m to 65 m. Below the saprolite is a layer of saprock, generally

less than 1 to 2 m thick. Beneath the saprock, bedrock is subdivided into CLB

(carbonate leached bedrock) and CSB (carbonate stable bedrock).

The results of BGC’s geotechnical investigation were used by SNC-LAVALIN for the

feasibility level design of the Tailings Management Facility (TMF). In addition, SNCLavalin

carried out analysis of samples collected from the sand and gravel deposit in

the tailings area. Results show that the sand and gravel is suitable material for filter,

drainage and other granular usages.

1.8.2 Tailings Dike Design and Construction Concepts

Design criteria for the TMF were selected to optimize groundwater protection,

physical stability and mine closure conditions, and to make maximum use of mine

waste materials on a cost effective basis. Due to the presence of cyanide in the

tailings slurry, the TMF was designed to withstand a maximum credible earthquake

and to contain the runoff from a 24 hour probable maximum flood event, based on

internationally and nationally accepted practice and risk ratings.

A cyanide destruction plant will be built to treat the Weak Acid Dissociable cyanide

concentration in the water discharged with the tailings slurry. It is not expected that

treatment of an acidic runoff will be required during mine operations.

Previous studies by BGC (BGC, 1996) identified a tailings facility comprised of two

cells. A two celled facility is no longer required due to changes in mining plan and

therefore, a single celled facility is proposed. In addition, the proposed dike

alignment differs from that proposed by BGC. The tailings dike does not extend as

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

26

far south as the previous layout since there is an area of sand and gravel deposit

along the old south dike perimeter. This material is not suitable as a foundation

material and therefore, the alignment was adjusted.

The alignment of the Tailings Dike was selected to provide a natural low permeability

foundation, to provide sufficient storage for tailings and water management, and to

utilize available natural topographic conditions.

The Starter Dike will form the first stage before operations begin and subsequent

stages will be constructed during operations. The Starter Dike will be sized to

provide tailings storage and water management for the first three years of operation.

It will be of low permeability design with foundation preparation and seepage control

measures for adequate structural and hydraulic stability. The TMF basin floor is

saprolite 20 m to 40 m thick with permeabilities ranging from 8x10

-5 to 3x10-7

cm/s

which will provide highly competent containment of contaminants.

The Tailings Dike will be raised in stages using mine waste materials from open pit

stripping. The ultimate crest elevation of the Tailings Dike provides storage for 243.1

Mt of tailings. Crest raising by the centreline method of construction will involve fill

placement on the tailings beach for the upstream part of the lift. To facilitate this,

tailings discharge will be carried out from the dike crest. The Tailings Dike is

designed so that supernatant water and runoff reporting to the tailings pond are

recycled for use in the mill process. Water will be pumped to the plant using a

reclaim water barge.

An emergency spillway is provided to safeguard the dike in the event of unexpected

climatic conditions or operational constraints. The emergency spillway will be

constructed in the south east corner of the TMF and will be raised as the dike is

raised.

Seepage analyses were carried out to estimate the seepage through the Tailings

Dike for the purpose of sizing the chimney and finger drains as well as the perimeter

collection ditch. Stability analyses were carried out using parameter values based on

analyses carried out by BGC as reported in the Feasibility Report (BGC, 1996). The

dike structure is stable under various loading conditions and suitable for post-closure

environment.

The minimum and maximum normal operating volumes used for design of the tailings

pond are 500,000 m

3 and 3,000,000 m3

. The minimum normal operating volume

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

27

provides sufficient water depth to meet barge and reclaim pumping requirements, as

well as settlement of solids. The maximum normal operating volume is based on the

seasonal fluctuation in precipitation and the water treatment plant capacity. In

average conditions, the maximum water level will occur in the tailings pond during the

month of September, at the end of the wet season.

To ensure dike safety and satisfactory performance as tailings depository,

instrumentation is required to be installed in the dike structure. This includes pore

water pressure monitoring, settlement monitoring and groundwater monitoring during

operation and post-closure.

1.9 Administration and Operations

Buckland Harapiak (B-H) was engaged by Crystallex to carry out a study and make

recommendations for the appropriate organization structure for the Las Cristinas

operation, with a particular focus on the Finance & Administrative functions. The

organization proposed would support the 20,000 t/d open pit mine and CIL

processing facility with a total work force of approximately 400 employees. Research

for this report included interviews with senior management from Crystallex, including

in-country management; feasibility work previously completed by SNC-Lavalin and

MDA; the 1996 Socio-Economical Study conducted on behalf of PDI; the Las

Cristinas Development Plan (presented earlier this year by Dr. Sadek El-Alfy and

Julio Rojo) and various other sources of information on Venezuela and comparable

mining operations around the world.

1.10 Environmental Management

1.10.1 Introduction

A number of conclusions and recommendations can be drawn from environmental

analyses and the preliminary assessment of the potential environmental impacts

conducted during the feasibility stage of the Las Cristinas Project, as well as

development of the preliminary concept for site closure and rehabilitation.

A detailed Environmental Impact Assessment of the Las Cristinas project is required

by both Venezuelan and World Bank requirements. A significant amount of

environmental baseline data and impact analysis necessary for EIA preparation was

undertaken by PDI throughout the early to mid 1990’s. PDI submitted an EIA

document to the Venezuelan Government for review and approval in 1996, and a

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

28

Land Occupation permit was issued for the project. Building on the work conducted

by PDI, and in consultation with the Venezuelan Ministry of Environment and Natural

Resources, Crystallex initiated an update of the PDI work during the feasibility stage

of their project development to reflect changes in project design and environmental

characteristics. The main environmental activities of SNC-Lavalin and Crystallex

during this feasibility stage were:

Review of the Venezuelan environmental permitting and approval process

and standards/guidelines of the World Bank to ensure that regulatory and

Bank requirements are addressed/accounted for in the project development

schedule and work plan, and project design;

Initial consultation with the Ministry of Environment and Natural Resources;

Initial consultation with local community leaders and residents, including a

preliminary social survey;

Collection and review of all available PDI documents and databases and

other available published data;

Additional acid base accounting testing of waste rock and ore materials;

Updating of the demographic data for the local and regional communities

incorporating 2001 census data;

Review of the (revised) Crystallex project design and assessment of potential

environmental impacts and measures that can be reasonably implemented to

minimize or eliminate environmental effects;

Development of a preliminary site closure concept;

Establishment of objectives and guidelines for the development of an

Environmental Management Plan

Interaction with project designers to ensure that mitigation measures

identified to minimize/eliminate impacts have been incorporated into project

design concepts and capital/operating cost estimates; and

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

29

Identification of studies and testing that must be undertaken in subsequent

stages to provide the data necessary to further assess potential risk and

address concerns at a more detailed level of design.

A revised/updated EIA, Site Closure and Rehabilitation Plan and Environmental

Management Plan that meets Venezuelan and World Bank standards will be

prepared in the next stage of project development.

1.10.2 Conclusions

The following are key conclusions of the preliminary environmental impact

assessment and preliminary site closure and rehabilitation concept for the Las

Cristinas project:

Risk of significant environmental contamination from effluent discharges is

low

The Las Cristinas project can be developed in a manner which minimizes impacts to

the physical and biological environment.

The Las Cristinas project is being designed in accordance with applicable

Venezuelan legislation and regulations, and World Bank standards.

Crystallex has committed to the removal and controlled management/disposal of

mercury contaminated soils in a contained landfill facility, potentially resulting in

improvements to local water quality and reduced mercury load in local fish.

Initial acid base accounting (ABA) tests conducted on representative samples of

waste rock and ore composites indicate that almost 60% of waste rock (oxidized

saprolite and carbonate bedrock) will be non-acid generating and approximately 20%

of waste rock (sulphidic saprolite) will be acid generating; the waste rock dumps will

be designed to ensure that acid generating waste is placed over the low permeability

saprolite soils (to retard downward migration into subsurface soils and ground water)

and covered/buffered by non-acid generating or net acid consuming waste.

As precipitation exceeds evaporation over the course of a full annual cycle, there will

be a net discharge of water from the Las Cristinas site, however the site is being

designed and can be operated to effectively manage site drainage in a manner which

prevents erosion and ensures that all site effluent discharges to surface receivers will

meet Venezuelan and World Bank standards.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

30

An SO

2

/air cyanide destruction plant is included in process plant design; the plant will

treat all reclaim from the tailings management facility prior to use in the process.

Excess treated water (reclaim which is not required for the process) will be released

to the environment as surface discharge. The CN

wad

concentration of this effluent is

unknown at this early stage of design (until further design and operating details are

provided for the cyanide destruction plant). If concentrations cannot be reasonably

reduced to levels which comply with the Venezuelan regulations and World Bank

standards (0.5 mg/L CN

wad

) the destruction plant could be reoriented to treat tailings

as they exit the plant, for storage in the TMF facility.

Treated effluent from the sewage treatment plant will be discharged to the tailings

management facility during periods of low flow (dry season).

Sludges generated at the sewage treatment plant, the potable water plant and (later

if necessary) the ARD treatment plant will be stored in the tailings management

facility, adding less than 2% to total volume over the operating life of the facility.

Periods of flooding and potential site inundation may result in over-topping of site

runoff ponds; dilution from these flood waters is expected to minimize any concern of

contamination.

Risk Of Tailings Management Facility (TMF) Failure or Environmental

Contamination is Low

The Las Cristinas site area is in seismic activity zone 0 which presents the lowest

possible risk of seismic activity.

The TMF dam is designed to a stability factor of 1.3 (initial) and 1.5 (final

configuration and closure condition), which exceeds Venezuelan, European Union,

and Canadian dam association standard of 1.1.

The TMF is designed to contain a 24 hour Probable Maximum Precipitation flood

(PMF).

The tailings dam structure is designed to include a low permeability “clay” core

(saprolite soils) with a lower permeability hard rock shell on the downstream face. A

chimney drain and finger drains will be provided to minimize head build-up and

dangerously high phreatic head levels in the tailings; dam seepage will be collected

in a perimeter drain and released or re-circulated by a series of perimeter sumps

back to the tailings pond for long-term storage. Estimated seepage rate will be

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

31

approximately 11 m

3/hr for the starter dam and 157 m3

/hr for the ultimate

configuration.

The entire tailings basin will be cleared of vegetation and founded on a low

permeability saprolite soil layer with an average conductivity rate of 1 x 10

-6

cm/s,

and an average layer thickness of 30 m to 40m, providing a competent containment

barrier to contaminant migration.

The tailings dam “clay” core will be keyed into the low permeability saprolite soils,

preventing any inadvertent by-pass through intermittent sand or gravel lenses.

Permitting Expected to be Straightforward

The Las Cristinas project can be developed in a manner which meets Venezuelan

environmental standards.

The government of Venezuela and the President of the Republic have indicated their

repeated support for the Las Cristinas project, and other mining projects in Bolivar

state.

The Ministry of Environment and Natural Resources (MARNR) has indicated verbally

that EIA requirements for the Las Cristinas project can be met with submission of a

summary of updates and revisions to the PDI environmental impact assessment,

submitted and approved by MARNR in the late 1990s; no significant regulatory

hurdles are expected.

Crystallex maintains routine on-going discussions with CVG, MARNR and local

political leaders; issues are identified early and addressed as quickly as possible;

there are no known concerns on the part of any government agency or political party

that would present a significant risk of opposition to the project.

Leaders of the 6 main unions whose membership incorporates most of the small

miners operating within the Las Cristinas concessions indicated verbal support for

the project during recent interviews.

60% of surveyed residents in the local villages of Nuevas Claritas, Santo Domingo

and Las Claritas, support the Las Cristinas project if they can either continue with

mining activities or are provided another source of employment income.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

32

Crystallex has committed to providing technical assistance to small miners and will

be examining alternate employment opportunities for small miners in the next stage

of project design. Crystallex has also committed to meeting Venezuelan and World

Bank standards.

CVG is required by law to provide assistance in preventing the re-settlement of small

miners within the concession once the site has been cleared for Crystallex

operations.

Risk of contamination following closure is low

A detailed site closure and rehabilitation plan will be prepared in the next stage of

project design.

The preliminary concept for site closure and rehabilitation at closure is developed on

the basis that final land use for the site area will be natural, consistent with objectives

for the Imataca Forest Reserve.

Crystallex will maintain an active presence at the site for an undefined interim period

following termination of mine production, and prior to “walking away” from the site.

During this period they will operate an ARD treatment plant (if considered

necessary), and all site drainage necessary to ensure that ARD effluents are not

released to the environment untreated. All essential services such as access roads,

some buildings and some power supply will be maintained during the interim period.

All buildings, equipment, roads, and above ground services (e.g., transmission lines;

water supply lines, pumps, etc.) will be removed at closure (at latest following the

active interim closure period), and all slopes will be graded for public safety and

establishment of vegetation. Non-essential dams and berms will be breached and

graded to blend in with surrounding topography. The interim period will end once

Crystallex can demonstrate that all slopes are physically stable and that all site

drainage can be released to the environment without treatment in compliance with

Venezuelan and World Bank water quality standards.

1.10.3 Overall conclusion

In summary, it is concluded at this stage that the risk of significant environmental

impacts and/or schedule delays arising from environmental or socio-economic

concerns, either during operation, or following closure, is considered to be low.

Additional studies and analyses at a higher level of detail will be conducted in

subsequent stages of development to confirm these conclusions.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

33

1.10.4 Recommendations

A number of recommendations for specific work tasks to be conducted in subsequent

design stages are considered routine (such as preparation of a detailed

environmental impact assessment), and are not provided in the following summary.

A work plan which contains these activities will be developed by Crystallex prior to

initiating the next stage of design. The recommendations provided below are those

which are considered most significant in the consideration of project feasibility.

It is recommended that Crystallex conduct additional acid base accounting and longterm

static tests to confirm results of the initial acid generation potential testing

conducted during the feasibility stage; details of the test program will be developed at

the outset of the next stage of project design.

It is recommended that Crystallex conduct additional interviews and surveys of the

local political leaders, residents, and business operators (including the small miners)

to obtain input on the potential social and economic impacts of the project (positive

and negative), as well as development of an action plan which will address

mitigation/compensation required to offset impacts caused as a result of lost

employment once the small miners are permanently removed from the Las Cristinas

concessions. These activities should be conducted in the context of a broader

action plan program in accordance with established World Bank procedures.

Although not specifically required by Venezuelan regulation, it is recommended

during the next stage of project design that Crystallex arrange for, hold and attend a

series of community meetings in strategic locations throughout the zone of influence

to describe the Las Cristinas project and receive public feedback on potential impacts

of the project and measures which could be implemented to minimize the

significance of potential impacts.

1.11

1.11

1.11

1.11 Capital Cost Estimates

The Las Cristinas project capital costs are summarized in the Table 1-7.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

34

Table 0-7 Summary of Capital Cost

Item Estimated Cost (US$ x 1,000)

Mine 27,258

Process Plant 80,196

Tailings Management Facility 25,490

Infrastructure 27,728

Sub-Total Direct Costs 160,672

Owner’s Costs 10,000

Indirect Costs 72,095

Total Costs 242,767

In addition, sustaining capital totalling $160 million over the 34 years of the mine will

be required.

These estimates do not include VAT of $38.8 million which is recoverable once gold

sales commence.

1.12 Operating Cost Estimates

The estimated Operating Costs for the project, based on life of project averages are

in Table 1-8 as follows (before royalties):

Table 0-8 Operating Cost Estimates

Item Operating Cost/t Ore Operating Cost /oz Gold *

Mining $2.944 $80.01

Processing $3.378 $91.80

G & A $0.381 $10.37

TOTAL $6.704 $182.18

Note: *Does not include royalties

1.13 Financial Analysis

The findings in Table 1-9 were generated by the financial analysis using a gold price

of $325/oz.

334372 – Las Cristinas Feasibility Study

F:\LC Executive Summary September 4 2003 I.Doc

35

Table 0-9 Financial Summary

Cumulative Project Cash Flow $ 742 million

IRR Project (without debt financing, before VAT and taxes) 14.5%

NPV Project cash flows @ 5% $ 238.5 million (before taxes)

Payback Period-Years (from start of project) 5 years (before tax)

PLEASE NOTE:

THE ESTIMATES DESCRIBED IN THIS STUDY QUALIFY AS RESERVES IN

2
Jul 09, 2009 01:29PM
1
Jul 09, 2009 06:55PM
15
bmh
Jul 09, 2009 07:51PM
8
bmh
Jul 09, 2009 08:33PM
1
bmh
Jul 09, 2009 11:17PM

bmh
Jul 09, 2009 11:54PM
1
Jul 10, 2009 11:01AM
8
bmh
Jul 10, 2009 09:26PM
4
bmh
Jul 10, 2009 10:04PM
7
bmh
Jul 14, 2009 05:30PM
Share
New Message
Please login to post a reply