Sierra Metals Announces Production Results For The Third Quarter Of 2013
posted on
Oct 11, 2013 09:22AM
Friday, October 11, 2013
VANCOUVER, Oct. 11, 2013 /CNW/ - Sierra Metals Inc. (TSX:SMT)(BVL:SMT) ("Sierra Metals" or the "Company") is pleased to announce its production results for the third quarter of 2013.
Press Release Highlights:
Daniel Tellechea, President and CEO of Sierra Metals, commented: "Sierra's production during the third quarter has been lower than expected due to delays in the ramp up to 2,000 tonnes per day at Bolivar and higher dilution in head grades at Yauricocha. Consequently, we are revising our 2013 production guidance. However, we expect our fourth quarter production to improve given that we plan to achieve the production ramp up at Bolivar and we expect higher head grades at Yauricocha."
Revised Production Guidance
The Company has revised its production guidance for 2013 mainly as a result of 1) heavy rains and delays in the installation of the power substation needed to double production at Bolivar to 2,000 tonnes per day. Consequently, Sierra has ramped up production at Bolivar five months later than originally planned; and 2) higher dilution in head grades at Yauricocha resulting from unusual levels of water in mine production. The Company has engaged SRK Consulting to assist Yauricocha with this matter and expects to report improvements during the fourth quarter of 2013.
The New Guidance for the Company's metal production during 2013 is as follows:
Consolidated Production | Year-to-Date | New Guidance 2013 | Old Guidance 2013 | ||
Sep 30, 2013 | 4th Quarter | Full-Year | Low | High | |
Silver production (oz) | 1,906,763 | 715,000 | 2,621,763 | 2,582,000 | 2,922,000 |
Copper production (000 lb) | 11,086 | 5,600 | 16,686 | 20,400 | 23,100 |
Lead production (000 lb) | 26,678 | 9,000 | 35,678 | 42,400 | 48,000 |
Zinc production (000 lb) | 38,365 | 12,600 | 50,965 | 53,700 | 60,700 |
Gold Production (oz) | 5,071 | 1,300 | 6,371 | 6,000 | 7,000 |
Mine Operations
During this period, the Company achieved a total of 290,296 tonnes of ore processed (compared to 317,356 tonnes in 2012) from all operations, representing a 9% decrease year-over-year. Total tonnes processed of 931,684 in the first nine months of 2013 compared to 936,844 tonnes in the same period of 2012.
The decrease in production at the Yauricocha Mine during the third quarter was partially offset by strong production results in: (1) higher ore processed at Cusi, which achieved commercial production in January 1, 2013, and (2) higher head grades and recoveries at Bolivar. Both of these achievements are part of the Company's growth strategy to expand production in Mexico during 2013. A summarized table of consolidated production results is presented below:
Consolidated Production | 3 Months Ended | 9 Months Ended | ||||
Sep 30, 2013 | Sep 30, 2012 | % Var. | Sep 30, 2013 | Sep 30, 2012 | % Var. | |
Silver production (oz) | 626,735 | 681,846 | -8% | 1,906,763 | 1,936,836 | -2% |
Copper production (000 lb) | 3,270 | 3,517 | -7% | 11,086 | 11,517 | -4% |
Lead production (000 lb) | 8,591 | 10,009 | -14% | 26,678 | 27,024 | -1% |
Zinc production (000 lb) | 12,284 | 15,402 | -20% | 38,365 | 44,306 | -13% |
Gold Production (oz) | 1,673 | 2,409 | -31% | 5,071 | 8,310 |
-39% |
Yauricocha Mine, Peru
The Yauricocha Mine continued to be the Company's largest producing mine with a total of 201,769 tonnes processed in the third quarter of 2013 representing a 9% decrease compared to 221,033 tonnes in 2012. Total tonnes processed of 623,043 in the first nine months of 2013 compared to 650,048 tonnes in the same period of 2012. A 4% decrease year-over-year. Mineralization at the Yauricocha Mine is hosted in two different zones including Lead-Oxide ("Oxides") and Polymetallic ore-bodies.
During the third quarter of 2013, aggregate production of these ore bodies was 447,145 oz of silver, a 20% decrease year-over year; 1.5 million lb of copper, a 29% decrease year-over-year; 8.3 million lb of lead, a 15% decrease year-over year; 12.3 million lb of zinc, a 13% decrease year-over year; and 1,673 oz of gold, a 31% decrease year-over-year. Lower metal production was driven by lower head grades in line with Yauricocha's mine plan and higher dilution due to unusual levels of water in mine production. A summary of production from the Yauricocha Mine for the third quarter of 2013 has been provided below:
Yauricocha Production1 | 3 Months Ended | 9 Months Ended | ||||
Sep 30, 2013 | Sep 30, 2012 | % Var. | Sep 30, 2013 | Sep 30, 2012 | % Var. | |
Silver production (oz) | 447,145 | 559,719 | -20% | 1,402,805 | 1,596,858 | -12% |
Copper production (000 lb) | 1,458 | 2,043 | -29% | 5,347 | 6,889 | -22% |
Lead production (000 lb) | 8,338 | 9,825 | -15% | 26,099 | 26,629 | -2% |
Zinc production (000 lb) | 12,268 | 14,135 | -13% | 37,435 | 36,085 | 4% |
Gold Production (oz) | 1,673 | 2,409 | -31% | 5,071 | 8,310 | -39% |
1For a detailed summary of production table for the Yauricocha Mine please click here.
Bolivar Mine, México
During the third quarter of 2013, total ore processed at the Bolivar Mine decreased 13% with 62,329 tonnes processed compared to 71,239 tonnes in 2012. Total tonnes processed of 225,191 in the first nine months of 2013 compared to 219,249 tonnes in the same period of 2012. A 3% increase year-over-year. Copper production during the period increased 23% with a total of 1.8 million lb produced (compared to 1.5 million lb in 2012). Silver production at Bolivar increased 34% year over-year with a total of 52,498 oz produced (compared to 39,239 in 2012). This substantial increase in production was a result of higher grades and recovery rates year-over year. A summary of production for the Bolivar Mine for the third quarter of 2013 has been provided below:
Bolivar Production1 | 3 Months Ended | 9 Months Ended | ||||
Sep 30, 2013 | Sep 30, 2012 | % Var. | Sep 30, 2013 | Sep 30, 2012 | % Var. | |
Copper production (000 lb) | 1,812 | 1,473 | 23% | 5,739 | 4,627 | 24% |
Zinc production (000 lb) | 16 | 1,267 | -99% | 930 | 8,221 | -89% |
Silver production (oz) | 52,498 | 39,239 | 34% | 180,597 | 136,142 | 33% |
1For a detailed summary of production table for the Bolivar Mine please click here.
Cusi Mine, México
On January 1, 2013 the Company announced that the Cusi Mine achieved commercial production and during the third quarter of 2013 total ore processed increased 4% with a total of 26,198 tonnes of ore processed (compared to 25,084 tonnes in 2012). Total tonnes processed of 83,450 in the first nine months of 2013 compared to 67,547 tonnes in the same period of 2012. A 24% increase year-over-year. During the third quarter of 2013 production of silver at Cusi increased 53% with a total of 127,093 oz of silver (compared to 82,888 oz in 2012). This increase is mainly driven by higher head grades versus the third quarter of 2012 (197.3 g/t Ag vs 158.1 g/t Ag). A summary of production for the Cusi Mine for the third quarter of 2013 has been provided below:
Cusi Production1 | 3 Months Ended | 9 Months Ended | ||||
Sep 30, 2013 | Sep 30, 2012 | % Var. | Sep 30, 2013 | Sep 30, 2012 | % Var. | |
Silver production (oz) | 127,093 | 82,888 | 53% | 323,362 | 203,836 | 59% |
Lead production (000 lb) | 253 | 185 | 37% | 579 | 395 | 47% |
1For a detailed summary of production table for the Cusi Mine please click here.
Currently, the Company is in the midst of a substantial exploration and development program at Cusi that will focus on expanding production from Promontorio and adding new production from the San Juan, Minerva and La India mines by the end of 2013. Additionally, the Company completed an updated NI 43-101 resource calculation on the property in the third quarter of 2013.
Quality Control
The technical content of this news release has been approved by Thomas L. Robyn, Ph.D., CPG, RPG, a Qualified Person as defined in NI 43-101.
About Sierra Metals
Sierra Metals Inc. is a Canadian mining company focused on production of precious and base metals from its Yauricocha Mine in Peru, its Bolivar Mine and Cusi Mine in Mexico. In addition, Sierra Metals is exploring several precious and base metal targets in Peru and Mexico. Projects in Peru include Adrico (gold), Victoria (copper-silver) and Ipillo (polymetallic) at the Yauricocha Property in the province of Yauyos and the San Miguelito gold properties in Northern Peru. Projects in Mexico include Bacerac (silver) in the state of Sonora, La Verde (gold) at the Batopilas Property in the state of Chihuahua, and Las Coloradas (silver) at the Melchor Ocampo Property in the state of Zacatecas.
The Company's shares trade on the Bolsa de Valores de Lima and the TSX under the symbol "SMT".
Forward-Looking Statements
Except for statements of historical fact contained herein, the information in this press release may constitute "forward-looking information" within the meaning of Canadian securities law. Other than statements of historical fact, all statements are "forward-looking statements", which involve various known and unknown risk and uncertainties and other factors, including market conditions that may affect the Company's ability to execute its current business plan and to continue to pay a quarterly dividend. Actual results might differ materially from results suggested in any forward-looking statements. The Company assumes no obligation to update the forward-looking statements, or to update the reasons why actual results could differ from those reflected in the forward-looking statements unless and until required by securities laws applicable to the Company. Additional information identifying risks and uncertainties is contained in filings by the Company with the Canadian securities regulators, which filings are available at www.sedar.com.
PDF available at: http://stream1.newswire.ca/media/2013/10/11/20131011_C9283_DOC_EN_31976.pdf
PDF available at: http://stream1.newswire.ca/media/2013/10/11/20131011_C9283_DOC_EN_31977.pdf
PDF available at: http://stream1.newswire.ca/media/2013/10/11/20131011_C9283_DOC_EN_31978.pdf
SOURCE: Sierra Metals Inc.
For further information:
For further information regarding Sierra Metals, please visit www.sierrametals.com or contact:
Daniel Tellechea
President & CEO
Sierra Metals Inc.
1 (866) 493-9646
Thomas Robyn
Senior Vice President, Exploration
Sierra Metals Inc.
1 (866) 493-9646