Key Timelines

The following table displays upcoming key milestones and their project completion dates. The milestones and their project completion dates are provided as a guideline only and are subject to change.



Milestone



Projected Date


Environmental Assessment Certificate - Tumbler Ridge


April, 2012


Environmental Assessment Certificate -Wildmare


May, 2012


EPC Selection Process - Tumbler Ridge


Q2, 2012


EPC Selection - Wildmare


Q4, 2012


Turbine Supply Agreement – Tumbler Ridge


Q2, 2012


Turbine Supply Agreement - Wildmare


Q3, 2012


Financial Close – Tumbler Ridge


Q3, 2012


Financial Close – Wildmare


Q4, 2012


Financial Close – Cloosh Valley


Q1, 2013


Commercial Operation Date – Tumbler Ridge


Q3, 2013


Commercial Operation Date – Wildmare


Q3, 2014


Commercial Operation Date – Meikle


Q4, 2014


Commercial Operation Date – Bullmoose


Q4, 2015


Commercial Operation Date – Cloosh Valley


Q1, 2016