Welcome To The First Uranium Corporation HUB On AGORACOM

Edit this title from the Fast Facts Section

Free
Message: Update on Environmental Authorization

Update on Environmental Authorization

posted on Feb 02, 2010 06:07AM

First Uranium Update on Environmental Authorization

	    Company Commences a Project Restructuring at MWS, Revises Ezulwini Mine
Plan and Undertakes Strategic Review

	    TORONTO and JOHANNESBURG, Feb. 2 /CNW/ - First Uranium Corporation
(TSX:FIU, JSE:FUM) (ISIN:CA33744R1029) ("First Uranium" or "the Company")
today announced that the Company has been engaged in intensive discussions at
the most senior levels with officials of the North West Provincial government,
including the Department of Agriculture, Conservation, Environment and Rural
Development ("NWDACE") regarding its decision to withdraw the Company's
environmental authorization ("EA") for the new Tailings Storage Facility
("TSF"). The TSF was designed to accommodate future tailings deposition at the
Mine Waste Solutions ("MWS") tailings recovery project in South Africa. While
the EA has not yet been reinstated, based on these recent discussions, the
Company is cautiously optimistic that the EA will be reinstated.
	    Gordon Miller, President and CEO of First Uranium, commented, "As a
result of the circumstances that have been precipitated by the unexpected
withdrawal of the environmental authorization for our future tailings
deposition site at MWS, management's key priorities are to resolve this
authorization issue as quickly as possible, seek strategic alternatives for
financing and the immediate restructuring of our operations."

	    Strategic Review, Project Restructuring and Capital Limitations

	    The announcement of the withdrawal of the EA has not only delayed
construction of the TSF, it has also disrupted certain well-advanced corporate
financing opportunities, which, along with the slower than expected production
buildup at the Ezulwini Mine, would, if alternative financing is not obtained,
severely compromise the Company's financial position. The Company is now
reviewing strategic alternatives, and is engaged in discussions with respect
to alternative financing opportunities.
	    Notwithstanding progress at its operations discussed below, the
continuing discussions regarding the EA and the continuing financing
discussions, the Company has taken action to delay future development
expenditures, particularly at its MWS tailings recovery operation as part of a
company-wide program to conserve capital.
	    The construction of the first uranium plant module will be concluded by
the end of February 2010, at which time commissioning will commence. The plant
is expected to commence production of ammonium diuranate ("yellowcake") during
the second half of calendar year 2010. While the construction of the third
gold plant was progressing ahead of schedule and due for completion in May
2010, as a result of the apparent withdrawal of the environmental
authorization for the TSF, construction and commissioning of the third gold
plant have been suspended.
	    Production at MWS will be scaled back from two gold plants to one at the
end of March 2010. The reduced production will enable the Company to maximize
the availability of its current deposition capacity until the permitting issue
has been resolved, but will also result in lower revenues and increase the
amount of financing required by the Company.
	    Under the revised construction schedule the MWS No. 5 Dam will provide
sufficient tailings deposition capacity for the one gold plant until the end
of December 2011. Subject to re-instatement of the EA and the receipt of
additional capital in the near term, the project will be able to continue
along its originally planned production trajectory of 35,000 ounces per
quarter.
	    In addition, the Ezulwini Mine development plan is ahead of schedule,
however, the mine production forecast has been revised in response to slower
than expected mine production ramp up to date and the capital constraints.

	    <<
	    MWS: Quarterly Tailings Recovery and Production Forecast
	    -------------------------------------------------------------------------
	                             Q1 2010   Q2 2010   Q3 2010   Q3 2010   Q4 2010
	                              Actual    Actual  Forecast    Actual  Forecast
	    -------------------------------------------------------------------------
	    Tonnes of ore
	     reclaimed (000s)          1,835     2,476     3,880     3,528     2,789
	    -------------------------------------------------------------------------
	    Average gold head
	     grade (g/t)                0.42      0.39      0.39      0.36      0.34
	    -------------------------------------------------------------------------
	    Gold plant recovery (%)      44%       44%       51%       53%       52%
	    -------------------------------------------------------------------------
	    Gold reclaimed (oz)       11,007    13,422    25,019    21,891    15,844
	    -------------------------------------------------------------------------
	    Note: The increase in gold recoveries is possible through the
	    introduction of gold concentrates into the uranium plant where exposure
	    of material to an acidic environment liberates additional gold that
	    would otherwise not be available for cyanidation.
	    -------------------------------------------------------------------------
	    >>

	    At MWS, the Q3 2010 gold produced was less than forecast as the grade
reconciliation in the Buffelsfontein No. 4 Dam was slightly below expectations
and operations were interrupted by heavy rain storms during the quarter.

	    The annualized production rate presented below assumes a protracted
permitting process during which MWS runs at an average reduced throughput of
600,000 tonnes per month until January 2012. The ability to secure the EA, as
well as funding, sooner will allow acceleration of the annualized gold
production rate to 140,000 ounces per annum and uranium production to 960,000
pounds per annum as originally planned. From the point at which the EA and
funding are secured, MWS will require a six-month window to conclude the
necessary construction activities to realize the increased production rate.

	    <<
	    MWS: Annual Production Forecast
	    -------------------------------------------------------------------------
	                                                           FY 2011   FY 2012
	    -------------------------------------------------------------------------
	         Gold
	    -------------------------------------------------------------------------
	    Production (oz)                                         57,000    64,000
	    -------------------------------------------------------------------------
	    Estimated cost ($/oz)                                      459       490
	    -------------------------------------------------------------------------
	        Uranium
	    -------------------------------------------------------------------------
	    Production (lb)                                        270,000   560,000
	    -------------------------------------------------------------------------
	    Estimated cost ($/lb)                                       43        36
	    -------------------------------------------------------------------------
	    Note:
	    1.   Gold "Cash Costs" are costs directly related to the physical
	         activities of producing gold and include mining, processing and
	         other plant costs; third-party refining and smelting costs;
	         marketing expense, on-site general and administrative costs;
	         royalties; on-mine drilling expenditures that are related to
	         production and other direct costs. Sales of by-product metals are
	         deducted from the above in computing cash costs. Cash costs exclude
	         depreciation, depletion and amortization, corporate general and
	         administrative expense, exploration, interest, and pre-feasibility
	         costs and accruals for mine reclamation. Cash costs are calculated
	         and presented using the "Gold Institute Production Cost Standard"
	         applied consistently for all periods presented. The Gold Institute
	         was a non-profit industry association comprised of leading gold
	         producers, refiners, bullion suppliers and manufacturers. This
	         institute has now been incorporated into the National Mining
	         Association. The guidance was first issued in 1996 and revised in
	         November 1999. Total cash costs per ounce is a non-GAAP measurement
	         and investors are cautioned not to place undue reliance on it and
	         are advised to read all GAAP accounting disclosures presented in
	         the Corporation's audited consolidated financial statements for
	         FY 2009 and accompanying footnotes thereto.
	    2.   Uranium "Cash Costs" calculations take into account the incremental
	         ounces of gold recovered when the ore is run through the atmospheric
	         leach tanks of the uranium plant.
	    -------------------------------------------------------------------------
	    >>

	    OUTLOOK - EZULWINI MINE

	    Production build up at the Ezulwini mine is progressing more slowly than
originally anticipated due to the challenges of training and building up the
efficiency of the mining crews with the result that the mine has yet to
generate positive operating cash flow. Based on the performance to date and
the Company's current cash position, the Ezulwini mine plan has been revised
as reflected below.

	    <<
	    Ezulwini Mine: Quarterly Underground Production Forecast
	    -------------------------------------------------------------------------
	                             Q1 2010   Q2 2010   Q3 2010   Q3 2010   Q4 2010
	                              Actual    Actual  Forecast    Actual  Forecast
	    -------------------------------------------------------------------------
	    Upper Elsburg Mining
	     Activity
	    -------------------------------------------------------------------------
	    Cumulative metres of
	     mining face available       369       605       749     1,672     1,817
	    -------------------------------------------------------------------------
	    Blasted face grade -
	     gold (g/t)                 4.66      7.79      6.43      7.42      7.33
	    -------------------------------------------------------------------------

	    -------------------------------------------------------------------------
	    Middle Elsburg Mining Activity
	    -------------------------------------------------------------------------
	    Cumulative metres of
	     mining face available       408       754     1,131     1,024     1,311
	    -------------------------------------------------------------------------
	    Blasted face grade -
	     gold (g/t)                 2.95      3.13      3.06      3.20      3.28
	    -------------------------------------------------------------------------
	    Blasted face grade -
	     uranium (g/t)               480       439       552       557       560
	    -------------------------------------------------------------------------

	    -------------------------------------------------------------------------
	    Facelength ("FL") Buildup
	    -------------------------------------------------------------------------
	    Gold (kg/m of FL blasted)     15        28        75        81        91
	    -------------------------------------------------------------------------
	    Uranium (kg/m of
	     FL blasted)               1,077     1,377     3,328     2,862     3,690
	    -------------------------------------------------------------------------

	    -------------------------------------------------------------------------
	    Mill Production (combined)
	    -------------------------------------------------------------------------
	    Tonnes of ore milled (000s)   92        95       145       117       137
	    -------------------------------------------------------------------------
	    Notes:
	    1.   Face-length buildup is a metric to indicate the content of gold and
	         uranium produced for a horizontal metre of blasted face length.
	    2.   The current mining rate is not expected to immediately fill the
	         uranium and gold plants that have production capacities of 100,000
	         tonnes per month and 200,000 tonnes per month, respectively.
	    3.   A minimum three-month delay is expected between uranium production
	         and sales, allowing time for calcining, shipment and conversion.
	    4.   The anticipated increase in stope grades has been determined on the
	         basis of current in situ sampling of reef development and sampling
	         of new stopes that are being opened up.
	    5.   The forecast face length represents the amount of face length
	         available for mining, not necessarily what will be mined.
	    -------------------------------------------------------------------------


	    Ezulwini Mine: Annual Production Forecast:
	    -------------------------------------------------------------------------
	                                                 FY 2011   FY 2012   FY 2013
	    -------------------------------------------------------------------------
	          Gold
	    -------------------------------------------------------------------------
	    Production (oz)                              133,000   194,000   265,000
	    -------------------------------------------------------------------------
	    Estimated by-product cash costs ($/oz)           909       672       634
	    -------------------------------------------------------------------------
	         Uranium
	    -------------------------------------------------------------------------
	    Production (lb)                              207,000   312,000   390,000
	    -------------------------------------------------------------------------
	    Estimated by-product cash costs ($/lb)            46        40        41
	    -------------------------------------------------------------------------
	    Notes:
	    1.   "Cash Costs" are costs directly related to the physical activities
	         of producing gold and include mining, processing and other plant
	         costs; third-party refining and smelting costs; marketing expense,
	         on-site general and administrative costs; royalties; on-mine
	         drilling expenditures that are related to production and other
	         direct costs. Sales of by-product metals are deducted from the
	         above in computing cash costs. Cash costs exclude depreciation,
	         depletion and amortization, corporate general and administrative
	         expense, exploration, interest, and pre-feasibility costs and
	         accruals for mine reclamation. Cash costs are calculated and
	         presented using the "Gold Institute Production Cost Standard"
	         applied consistently for all periods presented. The Gold Institute
	         was a non-profit industry association comprised of leading gold
	         producers, refiners, bullion suppliers and manufacturers. This
	         institute has now been incorporated into the National Mining
	         Association. The guidance was first issued in 1996 and revised in
	         November 1999. Total cash costs per ounce is a non-GAAP measurement
	         and investors are cautioned not to place undue reliance on it and
	         are advised to read all GAAP accounting disclosures presented in
	         the Corporation's audited consolidated financial statements for
	         FY 2009 and accompanying footnotes thereto.
	    2.   The face-length buildup is a metric to indicate the content of gold
	         and uranium produced for a horizontal metre of blasted face length.
	         The cash costs are shown on co-product basis, where costs are
	         allocated to each metal on the basis of the revenue contribution
	         from each metal.
	    -------------------------------------------------------------------------
	    >>


	    Q3 2010 PRODUCTION UPDATE

	    During the quarter ended December 31, 2009 ("Q3 2010"), the Company
produced 10,054 ounces of gold from the Ezulwini Mine, a 26% percent increase
compared to the previous quarter, and 21,891 ounces of gold from the Mine
Waste Solutions tailings recovery project ("MWS"), a 63% increase compared to
the previous quarter. During the quarter, the Company also continued to
optimize its uranium production at the Ezulwini Mine and has shipped its first
container of 23,760 pounds of uranium in the form of "yellowcake" (ammonium
diuranate) for processing in the United States.

	    <<
	    Quarterly Production Results
	    -------------------------------------------------------------------------
	                             Q3 2009   Q4 2009   Q1 2010   Q2 2010   Q3 2010
	    -------------------------------------------------------------------------
	    Ezulwini
	    -------------------------------------------------------------------------
	    Total tonnes of
	     ore milled               80,079   108,622    92,468    94,599   108,503
	    -------------------------------------------------------------------------
	    Gold produced (oz)         6,411     4,267     3,791     7,952    10,054
	    -------------------------------------------------------------------------
	    Gold sold (oz)             6,411     4,267     3,379     7,047     8,213
	    -------------------------------------------------------------------------
	    Uranium shipped to
	     converter (lb)                -         -         -         -    23,760
	    -------------------------------------------------------------------------

	    -------------------------------------------------------------------------
	    MWS
	    -------------------------------------------------------------------------
	    Tonnes of ore
	     reclaimed (000s)          1,798     1,693     1,835     2,476     3,528
	    -------------------------------------------------------------------------
	    Average gold head
	     grade (g/t)                0.42      0.41      0.42      0.39      0.36
	    -------------------------------------------------------------------------
	    Gold plant recovery (%)      50%       47%       44%       44%       53%
	    -------------------------------------------------------------------------
	    Gold reclaimed (oz)       12,235    10,513    11,007    13,422    21,891
	    -------------------------------------------------------------------------
	    Gold sold (oz)            12,581    10,417    10,676    11,739    21,091
	    -------------------------------------------------------------------------

	    In Q4 2010, MWS expects to:
	    -  commence commissioning of one flotation circuit and the uranium plant.
	       The remaining two flotation circuits, the third gold plant and the TSF
	       will be completed upon reinstatement of the EA and the receipt of
	       funding;
	    -  terminate the EPCM contract and dismiss all construction personnel
	       from the project; and
	    -  focus production on one of the existing gold plants for an estimated
	       quarterly production of 15,844 ounces of gold.

	    In Q4 2010, the Ezulwini Mine expects to:
	    -  open up over 400 metres (net of mining activity) for a total of over
	       3.1 kilometers of available mining face underground at the Ezulwini
	       Mine; and
	    -  record our first sale of uranium.
	    >>

	    Technical Disclosure

	    All technical disclosure in this news release relating to MWS has been
prepared in accordance with National Instrument 43-101 ("NI 43-101) by Jim
Fisher who is a Chartered Engineer and is a "qualified person" under NI
43-101.
	    All technical disclosure in this news release relating to the Ezulwini
Mine has been prepared in accordance with NI 43-101 by R. Dennis Bergen,
P.Eng., Associate Principal Mining Engineer, with Scott Wilson Roscoe Postle
Associates Inc. ("Scott Wilson RPA") who is a "qualified person" under NI
43-101 and is independent of First Uranium.

	    About First Uranium Corporation

	    First Uranium Corporation (TSX:FIU, JSE:FUM) is focused on its goal of
becoming a significant low-cost producer of uranium and gold through the
expansion of the underground development to feed the new uranium and gold
plants at the Ezulwini Mine and through the expansion of the plant capacity of
the Mine Waste Solutions tailings recovery facility, both operations situated
in South Africa. First Uranium also plans to grow production by pursuing
value-enhancing acquisition and joint venture opportunities in South Africa
and elsewhere.

	    Cautionary Language Regarding Forward-Looking Information

	    This news release contains and refers to forward-looking information
based on current expectations. All other statements other than statements of
historical fact included in this release including, without limitation,
statements regarding the timing and receipt of required permits, the timing
and availability of financing on acceptable terms, the timing and amount of
estimated future production, processing and development plans and future plans
and objectives of First Uranium are forward-looking statements (or
forward-looking information) that involve various estimates, assumptions,
risks and uncertainties. For more details on these estimates, assumptions,
risks and uncertainties, see the Company's most recent Annual Information Form
on file with the Canadian provincial securities regulatory authorities on
SEDAR at www.sedar.com. These forward-looking statements are made as of the
date hereof and there can be no assurance that such statements will prove to
be accurate, such statements are subject to significant risks and
uncertainties, and actual results and future events could differ materially
from those anticipated in such statements. Accordingly, readers should not
place undue reliance on forward-looking statements that are included herein,
except in accordance with applicable securities laws.






-30-
	    /For further information: Bob Tait, Vice President, Investor Relations at
bob@firsturanium.ca, (416) 342-5639 (office) or (416) 558-3858 (mobile),
1240-155 University Avenue, Toronto, ON, M5H 3B7/
Share
New Message
Please login to post a reply