Here is the map:
http://goldenhopemines.com/_resources/maps/location_map_2010_Trenches.pdf
The trenches were as follows:
The current program was carried out on three different zones including Timmins 1 (T1),
the Ascot/Road, and the 88 zones. A total of 280 metres of trenching was completed in 16
individual trenches. 5 trenches totaling 84.0 metres were completed on the T1 Zone, 2
trenches (18.0 metres) completed on the Ascot / Road Zone and 9 trenches (178 metres)
were completed on the 88 Zone. Drilling and blasting services were provided by Forages
La Chaudiere Inc. of St-Georges, Quebec. Crushing equipment was supplied and
operated by a local contractor, M. Paul Labrie of St-Magloire, Quebec.