IAMGOLD Announces Acceleration of Work at Westwood...
posted on
May 30, 2008 01:00PM
Edit this title from the Fast Facts Section
TORONTO, ONTARIO--(Marketwire - May 30, 2008) - IAMGOLD Corporation ("IAMGOLD" or "the Company") (TSX:IMG)(NYSE:IAG)(BOTSWANA:IAMGOLD) announces progress on the acceleration of its Westwood advanced exploration project located two kilometres from the Company's operating Doyon Mine within the prolific Abitibi region of Northern Quebec.
"The momentum behind the Westwood project continues to increase as the acceleration of the project becomes reality," stated Joseph Conway, President and CEO.
The activity currently taking place to accelerate the project includes the development of an exploration ramp, preparation for shaft sinking, infrastructure enhancements and a revised scoping study. The Company's primary objective regarding Westwood is to accelerate all aspects of the exploration program to reach a commercial production decision as soon as possible.
The first phase of the activity is to begin an exploration ramp to provide better drilling access to the upper levels of the deposit, above the current "14th level" exploration drift. Concurrent with ramp access is the development of the first phase for a possible 2,000 metre shaft. The process to obtain the environmental and other permits required has begun. They are expected to be granted in July. The drilling of a condemnation drill hole at the proposed shaft site is almost complete. Other facets of the shaft site preparation have also begun, including access roads and electric power lines. In addition, a letter of intent has been signed with a shaft sinking company to begin raise boring a 2.4 metre diameter hole to a depth of 865 metres in August 2008. Detailed engineering for shaft design has also begun. By the end of September 2008, a revised scoping study will be completed providing details on metallurgy, rock mechanics, reserves, resources, capital expenditure and timelines to a commercial production decision.
An important component of Westwood's development is to increase the confidence level of the current resources and to establish geologic continuity. A detailed definition drilling program was established in early 2008 to achieve this objective over a 350 metre by 350 metre block within the known Zone 2 resource. This drill program will be completed in June. Concurrently, a drift is being developed to assess the grade and the continuity of the ore zones contained in Zone 2 .This will provide material for additional metallurgical testing.
The results from the drilling campaign are being interpreted now and will be available with the update on resources scheduled for the month of July.
Table 1 outlines the latest results from the detailed drilling program in Zone 2. Significant results include:
- 30.5 g/t Au over 3.0 metres - Hole R14488-08
- 33.4 g/t Au over 5.0 metres - Hole R14488-08
- 12.0 g/t Au over 9.0 metres - Hole R14467-08
- 10 g/t Au over 4.0 metres - Hole R14461-08
- 24.4 g/t Au over 4.0 metres - Hole R14467-08
Particularly encouraging is the discovery of additional vein structures which have high gold value intercepts. The discovery of additional veins creates the potential for increases in the resource base beyond the 3.3 million ounce inferred resource outlined to date. A further update on results at Westwood will be provided in late June.
TABLE 1: RECENT DRILLING RESULTS FROM WESTWOOD
VALUATION PROGRAM ON ZONES 2 AND NORTH CORRIDOR
(SINCE START OF WORKS IN JANUARY 2008)
------------------------------------------------------------
Intersection Zone 2 Extension
-------------------------------------------------
True Au Type
from Core length width ---------------
Hole # (m) to (m) (m) (m) g/t Vein
------------------------------------------------------------
R14438-08 119.0 123.0 4.0 3.6 3.1 Z2-30
------------------------------------------------------------
R14439-08 123.0 126.0 3.0 3.2 9.3 Z2-30
------------------------------------------------------------
R14440-08 131.0 134.0 3.0 3.1 8.6 Z2-30
------------------------------------------------------------
R14441-08 123.0 126.0 3.0 3.2 5.8 Z2-30
------------------------------------------------------------
R14443-08 104.0 108.0 4.0 3.8 14.2 Z2-30
------------------------------------------------------------
R14444-08 145.0 148.5 3.5 3.3 1.3 Z2-30
--------------------------------------------------
182.0 186.0 4.0 3.5 17.6 Z2-40
--------------------------------------------------
205.5 209.0 3.5 3.0 5.2 Z2-50
------------------------------------------------------------
R14446-08 168.0 172.5 4.5 3.6 1.5 Z2-30
------------------------------------------------------------
R14447-08 109.5 113.0 3.0 3.1 9.5 Z2-30
--------------------------------------------------
135.5 138.5 3.0 3.0 8.8 New vein
------------------------------------------------------------
R14448-08 165.5 169.0 3.5 3.3 0.1 Z2-30
------------------------------------------------------------
R14450-08 120.0 123.0 3.0 3.1 5.3 Z2-30
------------------------------------------------------------
R14451-08 172.0 176.0 4.0 3.2 4.6 Z2-30
------------------------------------------------------------
R14453-08 136.5 140.0 3.5 3.3 7.7 Z2-30
--------------------------------------------------
197.5 200.5 3.0 3.0 6.0 Z2-40
------------------------------------------------------------
R14454-08 148.5 151.5 4.0 3.3 4.2 Z2-30
------------------------------------------------------------
R14455-08 137.0 140.5 3.5 3.3 0.5 Z2-30
--------------------------------------------------
369.0 372.5 3.5 3.0
--------------------------------------------------
401.5 405.5 4.0 3.0
------------------------------------------------------------
R14461-08 187.0 191.0 4.0 3.0 0.9 Z2-30
--------------------------------------------------
261.0 265.0 4.0 10.0 New vein
------------------------------------------------------------
R14462-08 104.0 107.5 3.5 3.0 7.6 Z2-30
------------------------------------------------------------
R14460-08 200.0 204.5 4.5 3.0 0.2 Z2-30
--------------------------------------------------
248.0 253.0 5.0 4.4 Z2-40
------------------------------------------------------------
R14465-08 118.8 122.0 3.2 3.0 4.2 Z2-30
------------------------------------------------------------
R14463-08 137.0 143.0 6.0 4.1 New vein
--------------------------------------------------
161.0 165.0 4.0 3.0 2.4 Z2-30
--------------------------------------------------
198.5 202.5 4.0 3.0 4.2 Z2-40
--------------------------------------------------
400.0 404.0 4.0
------------------------------------------------------------
R14464-08 105.0 109.0 4.0 3.0 4.1 Z2-30
--------------------------------------------------
177.0 180.0 3.0 3.0 7.7 Z2-40
------------------------------------------------------------
R14470-08 171.0 174.5 3.5 3.0 4.1 Z2-30
------------------------------------------------------------
R14466-08 107.2 110.5 3.3 3.0 0.8 Z2-30
------------------------------------------------------------
R14467-08 219.0 228.0 9.0 12.0 Z2-30
--------------------------------------------------
238.0 243.5 5.5 3.8 24.7 Z2-40
--------------------------------------------------
283.0 287.0 4.0 24.4 Z2-50
------------------------------------------------------------
R14468-08 104.0 107.5 3.5 3.0 0.1 Z2-30
------------------------------------------------------------
R14469-08 130.0 133.5 3.5 3.0 0.1 Z2-30
------------------------------------------------------------
R14471-08 165.0 169.0 4.0 3.0 3.0 Z2-30
------------------------------------------------------------
R14472-08 207.7 211.5 3.8 3.0 3.5 Z2-30
------------------------------------------------------------
R14473-08 182.5 186.0 3.5 3.0 1.7 Z2-30
------------------------------------------------------------
R14474-08 259.0 263.0 4.0 3.0 30.5 Z2-30
--------------------------------------------------
417.5 420.5 3.0 2.4 8.9 New vein
------------------------------------------------------------
R14475-08 88.0 91.5 3.5 3.0 0.5 Z2-30
------------------------------------------------------------
R14482-08 187.5 191.0 3.5 3.0 1.4 Z2-30
------------------------------------------------------------
R14483-08 Drillhole stopped in Bousquet fault
------------------------------------------------------------
R14488-08 216.0 220.0 4.0 3.0 30.1 Z2-30
--------------------------------------------------
220.0 227.0 7.0 5.0 33.4 Z2-40
--------------------------------------------------
272.0 276.0 4.0 3.0 18.3 Z2-50
------------------------------------------------------------
R14484-08 182.0 186.0 4.0 3.0 1.3 Z2-30
------------------------------------------------------------
R14485-08 254.0 258.5 4.5 3.0 14.1 Z2-30
--------------------------------------------------
318.0 323.0 5.0 3.5 20.1 Z2-50
------------------------------------------------------------
R14490-08 149.0 152.5 3.5 3.0 11.2 Z2-30
------------------------------------------------------------
R14492-08 184.5 188.0 3.5 3.0 2.7 Z2-30
------------------------------------------------------------
For more information, please contact