Re: Happy New Year - Retraction of my Prediction
in response to
by
posted on
Jan 05, 2010 11:39PM
Producing Mines and "state-of-the-art" Mill
If you look at Table 22 you will see that they used different cut off grades for each zone
(Pit 0.25%, SLC/BH 0.54%, CF 0.63%)
As you can see; they are targeting the higher grade (1.91%) Cut and Fill lower zone first from 2009 Q4 to 2010 Q4.
The middle zone and grade (0.68%) SubLevel Caving/Blast Hole will be mined over the 2yr LoM and the open Pit zone (0.33%) will be exploited from March-October 2010.
In my previous post I used an average for the cost per tonne of $62.00 and a Net Smelter percentage of 72.6. The estimated cost for the open pit is $25.61 and $56.96 for the SubLevel Caving, this along with a calculated SRK Net Smelter percentage of 81.04% makes mining the lower grades economical. One thing I should point out is that I'm questioning SRK's calculation of Xstrata's Ni and Cu participation and MgO Penalty calculations. If anyone could valid their numbers in table 22 and fill me in, I would very much appreciated it, thanks.
The other major point; if metal prices remain at the current level we will generate 10.5M $Can in cash flow by the end of June 30, 2010. Which should be adequate to repay the J.J. loan due July 2010.
At the bottom of the spreadsheet the tpd (tonnes/day) indicate that there will be plenty of milling capacity to handle as much of Redstone's ore as they can bring to surface for the next six months. This could easily generate an equal amount of revenue @ 250tpd of 2.2% ore without having to use the third ball mill until Q3 2010.
So my concerns about the Hart project timelines are lessened, although I still hope that they are not complacent and make sure that all permits are obtained promptly.
Enjoy.
Sincerely
BubaBob