Free
Message: Re: Check out the Timeline for DFS re: Thacker Pass

One more update... LAC did "announce" back on July 30 2020 that they have moved the date up to Q4 of 2020... just as Pavel previously pointed out in his poste on this HUB, however their published Timeline on their web site doesn't reflect this change as of just one minute ago when I last checked here on 9 August 2020.  This would be a delay in updating their published "Timeline" and maybe they will correct that and update their Timeline, however.....

And this has always been my point:  The company did publish a Timeline that was posted on their web site and left up there for months that referred to the release of the DFS for Thacker Pass as:  H1, 2020.

Thanks, Pavel, for your clarification re: the now published date for release of the DFS for Thacker Pass as Q4, 2020.

 

https://www.marketwatch.com/press-release/lithium-americas-announces-release-of-draft-environmental-impact-statement-for-thacker-pass-lithium-project-2020-07-30-61845945#:~:text=In%20response%20to%20the%20COVID-19%20pandemic%2C%20Lithium%20Americas,release%20results%20of%20the%20DFS%20in%20Q4%202020.

 

I would really like some feedback on this H1 2020 thing, because I can't be the only one on this Hub who took a look at the published Timeline on LAC's web site that was left up for several months.  

I actually don't object to the company changing the Timeline from H1 2020 to the now announced Q4 2020, but they should update their Timeline on the Thacker Pass information on their web site.  The company claims that the delay is due to the Corona virus situation.  I understand how that could interfere and does interfere with the dates they have projected for construction, but I don't see how it would delay the DFS.  They could have easily made adjustments to their DFS prior to 30 June since we were well into the Corona virus situation by then.

I see that the person who lifted my post here earlier today has already been raked over the coals by the usual raker on TOB and the usual epithets have been applied.  Business as usual, of course.  

Anyway, Pavel, I can always depend on you to catch the  smallest detail regarding LAC and you certainly proved my faith in you on this particular "detail".  

I think we have now firmly established that LAC has committed to Q4 now for the release of the Thacker Pass DFS.  Let's all hold their feet to the fire on this commitment.  It is, after all, an important milestone on the company's progress toward actual production at Thacker Pass.. an event that those who are Pumpers and those who are Circumspective Investors in LAC can jointly look forward to since it will benefit us both in most significant terms:  the Share Price!

Share
New Message
Please login to post a reply