posted on
Feb 26, 2022 12:29PM
Message: Oh boy.
"Federal Permitting Timeline
The Record of Decision (“ROD”) for Thacker Pass was received in January 2021 from the Bureau of Land Management (“BLM”), and in February 2021, claims were filed against the BLM to appeal the issuance of the ROD. In Q3 2021, injunction requests over the Company’s plan to begin cultural assessment and pre-construction work were denied, and subsequently, a motion to reconsider was also denied in late 2021. Recently, the Federal court partially approved a request for the inclusion of additional documents from the BLM. As a result of the additional documentation requests, the ROD appeal process is expected to be complete in Q3 2022."
___________________________________________________________
Emphasis on that last sentence: " As a result of the additional documentation requests, the ROD appeal process is expected to be complete in Q3 2022."
2 Recommendations
Loading...
Loading...
New Message
Please
login
to post a reply