WB , you are correct.  I misunderstood production versa finishing facilities:

 

"...Stage 1 production capacity of 40,000 tpa battery-quality lithium carbonate* §

 Commissioning is underway, lithium carbonate production expected in H1 2023

§ Wellfield and pre-concentration ponds operating at nameplate and building stock

§ Key areas of the processing plant commenced commissioning in Q3 2022 §

 Focus is on prioritizing production over completion of a portion of the purification process designed to achieve battery-quality lithium carbonate, deferred to the first half of 2023 § Transitioning the team from construction to operations with key hires and training..."