Not exactly sure what you're asking, but I hope this helps:
There is currently only one '336 reex request (90,011,168) that has yet to be determined.
It took 2 mnths and 23 days for the previous recert of the '336 to be published from the NIRC. That will bring us to Oct.10, 2010 for the current NIRC to be published using the same timeline.
The '584 had two new requests, 90/009,591, 90/011,169. The 1,169 reex was ordered yesterday and the 9,591 petition to re-open the previously denied (Nov.4, 2009) request was granted Sept. 8, 2010.
The '890 (90/009,388) had a final rejection on Apr. 29, 2010 that is being appealed.
The '749 (90/009,034) had a final rejection mailed Sept. 28,2010.
GLTAL