If this is verbatim from the news releases it does not say it was delayed 3 months. It simply says it delayed the teams progress. Over the last 3 months. Doesn't say how much just that it did ? I'm in the camp that says something else is coming, and soon !!
Regards
Crzyhors
"Beyond purely technical issues, the UCONN team had to deal with significant issues related to a new piece of equipment installed in late 2014 that was malfunctioning. This delayed the team’s progress in the last 3 months. The issue was resolved in the last week of March 2015 with the root cause identified as an inappropriate installation by a third party. Appropriate repairs to this equipment have been made. The team is confident to complete the three milestones over the course of the next quarter."