In double checking the published tender schedule, contract award was to happen sometime between June 4th and June 30th of this year, just around the time of the AGM. Perhaps they were hoping for the contract pre AGM, but it has yet to materialize. I’m not sure if this delay beyond June 30 is significant, or just a normal part of the Indian tendering process.
Seq No
|
Buyer Stage
|
Supplier Stage
|
Start Date & Time
|
Expiry Date & Time
|
1
|
Tender Release
|
-
|
08-07-2017 10:00
|
10-07-2017 16:00
|
2
|
-
|
Tender download
|
10-07-2017 16:01
|
25-08-2017 15:00
|
3
|
-
|
Bid Submission
|
10-07-2017 16:02
|
25-08-2017 15:30
|
4
|
Bid Sealing
|
-
|
25-08-2017 15:31
|
28-08-2017 15:30
|
5
|
-
|
Open Authorisation
|
28-08-2017 15:31
|
01-09-2017 11:30
|
6
|
Tender Opening
|
-
|
01-09-2017 11:31
|
11-09-2017 17:30
|
7
|
Tender Evaluation
|
-
|
01-09-2017 11:32
|
31-05-2018 17:30
|
8
|
Price Bid Opening
|
-
|
09-05-2018 17:15
|
30-06-2018 17:30
|
9
|
Price Bid Evaluation
|
-
|
04-06-2018 10:00
|
30-06-2018 17:30
|
10
|
PO Release
|
-
|
04-06-2018 10:01
|
30-06-2018 17:30
|