Some weeks ago I updated this list...
Based on :
- estimated fractime 2 weeks
- flowtest 4 weeks
- using the same frac crew
Leclercville (not Qec well, but important anyway because it lies between St.Edouard and Fortierville)
week 24 start frac'ing of Leclercville
week 26 start testing of Leclercville
week 30 results from Leclercville
Gentilly
week 27 start frac'ing of Gentilly
week 29 start testing of Gentilly
week 33 results from Gentilly
Fortierville
week 18 spudding of Fortierville
week 23/24 Fortierville TD
week 30 start frac'ing of Fortierville
week 32 start testing of Fortierville
week 36 results from Fortierville
Probably also spudding of St.Gertrude in June.
---
It is said that the frac crew is heading back to Alberta around July 10th. That means that the frac'ing of these wells wil be done ahead of my schedule. I will not cry if this turns out to be true :-)
Rgds
Domus