I think that the 20 ft/day may be a bit optimistic, the time line of January to 10 june, is appoximately 160 days when announcement was made. 2000/160=12.5 ft/d. not 20 and the further into ramp the longer the haul of rock out. probably reach it by month end realistically. This is not the start of mining. It is only the ramp progress to target area. Most likely another month before development for a bulk sample. JMHO