Current Status of Smoothe Prospect Well Currently Drilling
in response to
by
posted on
Dec 09, 2008 05:09AM
Edit this title from the Fast Facts Section
This is the current status of the Smoothe Prospect Block South Timbalier #49 well that Bayou Bend is currently drilling with Mariner Energy and Apache Corporation that Bayou Bends holds a 33.33% interest in. We are all putting our hopes on this well to bail out Bayou Bend at present. It appears that since November 24th the drill pipe got stuck and they have pulled it back uphole to 14143' feet to fix it. That is why we are being delayed as the well is planned for a total depth of 19,325' MD/18,300' TVD .
Cheers; Scott
http://sonlite.dnr.state.la.us/sundo...
WELLS
238366 | SL 340 | 007 | M224 | 6912 | 23 | 00 | 000 | 000 | 000 | 08/08/2008 | 17707201580000 |
08/08/2008 | 08/08/2008 | 01 |
0-0-0 | 0-0-0 | 1816530 | 285800 | 0 | S | NAD-27 |
605712.705631334 | 3258513.07986951 | -91.9099155061012 | 29.45158083467 |
08/08/2008 | 19000 | 19117 | 0 | 0 | 0 | 0 | 0 | 0 | 02 | 1816530 | 286662 | S | 01 | ||
08/08/2008 | 19000 | 19117 | 29 | 27 | 14.1 | 91 | 54 | 35.7 | 02 | 3097328 | 347368 | S | 02 |
238366 | SL 340 | 007 | M224 | 6912 | 01 | 00 | 08/08/2008 | 08/08/2008 |
12/08/2008 | 05 | 16275 | TSTD CSG; DRLD CMT TO 14223'; TAG CMT @ 14226'; SET CIBP @ 14176'; SET WHIPSTOCK @ 14138'; MILLED WHIPSTOCK WINDOW 14138-14143'; TIH W/ NEW WINDOW MILL BHA TO 14143' | |
12/01/2008 | 05 | 16275 | WORKED PIPE; ATTMTD TO PULL TO CSG SHOE & ESTABLISH CIRCULATION; STUCK PIPE @ 15544'; RIH W/ FREEPOINT TOOL, 60% FREE @ 15348'; POH TO 12459'; HOLE STARTED TAKING MUD; STABILIZED WELL; HUNG STRING OFF OF TST PLUG; CHANGED OUT TOP ELEMENT & TOP RAMS; RU & TSTD BOP'S; M&P 400 SXS CMT; BULLHEADED 345 BBLS OF OBM; EST TOC @ 14123'; WOC; | |
11/24/2008 | 05 | 16275 | DRLD; RE-LOGGED 15033-15184'; DRLD TO 16275'; GAINED 35 BBLS WHILE MAKING CONNECTION; SHUT IN WELL; PIPE STUCK; PUMPED KILL MUD; HAD NO COMMUNICATION W/ DP & ANNULUS; STRIPPED OUT OF HOLE TO 16098', TRYING TO ESTABLISH COMMUNICATION; | |
11/17/2008 | 05 | 14371 | DRLD; RAN 9 7/8" LNR FM 12612-14273' W/ 464 SXS; TSTD BOP'S; SERVICED TOP DRIVE; TSTD CSG; DRLG; | |
11/10/2008 | 05 | 14169 | RAN 11 7/8" LNR FM 12300-12920' W/ 281 SXS; RU & TSTD BOP'S; TSTD CSG & LNR; W&R; DRLG; | |
11/03/2008 | 05 | 13021 | DRLD TO 13021'; CIRC OBM & KILL WELL; CIRC & MONITORED WELL; RU 11 7/8" CSG EQUIPMENT, WELL BEGAN TO FLOW; SHUT IN WELL; RD CSG EQUIP; CIRC & MONITORING WELL; | |
10/27/2008 | 05 | 12914 | M&P 700 SXS CMT; DRLD CMT TO 12711'; DRLD NEW FORMATION TO 12712'; PERFORMED LEAK OFF TEST; MIXED, PUMPED, & SPOTTED 138 BBL BALANCED CMT PLUG @ 12710'; DRLD CMT TO 12712'; DRLD NEW FORMATION TO 12713'; PERFORMED LOT; DRLD TO 12914'; LOST RTRNS; PUMPED LCM PILL; | |
10/20/2008 | 05 | 12711 | RAN 13 5/8" CSG TO 12701' W/ 1218 SXS; NU & TSTD BOP'S; TSTD CSG; DRLD 10' NEW FORMATION; PERFORMED TWO LEAK OFF TESTS; SET FAS DRILL RTNR @ 10378'; RU SQZ EQUIPMENT; | |
10/13/2008 | 05 | 12701 | TSTD BOP'S; W&R; DRLD; W&R; CIRC; PREP TO RUN 13 3/8" CSG; | |
10/06/2008 | 05 | 11893 | DRLD TO 11893'; LOST FULL RTRNS; SPOTTED PILL; TSTG BOP'S; | |
09/29/2008 | 05 | 10577 | DRLG; | |
09/22/2008 | 05 | 8077 | ARRIVED ON LOCATION 9/17/08; RU & TSTD BOP'S 250/3500; RELEASED STORM PKR; W&R TO 6731'; DRLG; | |
09/15/2008 | 05 | 6731 | RETRIEVED 20" STORM PKR; RIH TO 3520'; CBU; RIH TO 6731'; CIRC OUT; PUMP SLUG & POH; SET PKR @ 198'; EVACUATED RIG; | |
09/08/2008 | 05 | 6731 | DRLD TO 6731'; EVACUATED FOR HC GUSTAV; RU 9/6/08; TSTG BOP'S; | |
08/25/2008 | 05 | 3807 | DRLD; W&R; RAN 20" CSG TO 3515' W/ 4424 SXS CMT; NU & TSTD BOP'S; TSTD CSG; DRLG; (BOP INFO: 21 1/4", 10M, TSTD 8/22/08 250/3500 PSI) | |
08/18/2008 | 05 | 3455 | DROVE 30" TO 352' W/ 303' OF PENETRATION; SPUD 8/14/08; DRLG; | |
08/08/2008 | 01 | 19117 | 6,809' FWL & 4,624' FNL OF BLOCK 214, SOUTH MARSH AREA. PBHL: 3,762' FNL & 6,809' FWL OF BLOCK 214, SOUTH MARSH AREA. |