Message: Re: SMH drill results
1
Apr 13, 2010 02:50PM

Apr 14, 2010 10:44AM

Yes. I am shareholder of Smh ,but work for another exploration co.

1 depends on depth of hole as to how long it takes.on average 40 metres a day

2 P.Geo must log-identify rock and what to assay

3 core must be cut in half,tagged bagged with blanks put in

Smh was 100 miles north of Red lake they are not going to run a few samples down to Red Lake .They would go when a truck is going back.Sometimes the P.Geo will not cut the core in this case because it is the 1st time it has been drilled;he may want a few holes to compare the rock.

4 If they used the Assay lab in Red lake;It would be prepared there and then shipped to the lab. that would do the assay which could be different places ie: Full Spectrum,Uranium,Moly maybe one place then it goes elsewhere to do silver ,Gold,etc. three places same company

5 Last ,but not least 21 to 28 days right now to get assays

6 small program you are going to put all the info out at the same time 100,000 metres every 4 to 8 holes


Apr 14, 2010 02:21PM
1
Apr 14, 2010 02:23PM
1
Apr 14, 2010 02:37PM

Apr 14, 2010 02:43PM

Apr 16, 2010 04:30PM

Apr 17, 2010 07:51AM

Apr 17, 2010 07:55AM
Share
New Message
Please login to post a reply