From Imperial Whazoo on another board:
"The concrete has been poured. The pre fab is being bolted together as we speak and the weather is fine. The curing of the concrete will be done Monday or Tuesday of next week. Upon curing, the machinery will take three days to bolt into place. The deisel costs are so low that the plant will be run under deisel power while waiting on Idaho Hydro to string the 25 miles of wires, so theres not going to be a hold up while the power company fiddle faddles.
And FINRA will soon finish delving into the backgrounds of the shareholder's listed as owners and, if they ask no further questions, then 14 days after the last wave of document requests, the uplist will be a done deal"
This is great news if true (IW has been quite reliable). So the equipment should be in place on the slab and the building partially, if not completely, erected by the end of the month. Should we look for mill startup by the end of December?