Message: Name Change

DAR Status - Letter from Tyhee to Mackenzie Valley Environmental Impact Review B

in response to by
posted on Apr 21, 2010 11:34AM

January 12, 2010 Via e-mail only to: vchristensen@mveirb.nt.ca

Mackenzie Valley Environmental Impact Review Board

Box 938

2nd Floor – 5102 - 50th Avenue

Yellowknife, NT

X1A 2N7

Attention: Mr. Vern Christensen, Executive Director, MVEIRB;

Re: Developers Assessment Report

Tyhee NWT Corp’s Yellowknife Gold Project

File EA0809-003

We have noticed that in the MVEIRB’s December 2009 monthly news letter it states:

“A proposed open pit gold mine, this project is located 88 kilometres north of

Yellowknife, near the former Discovery mine sit The Review Board is waiting for

Tyhee’s Developer’s Assessment Report, expected January 2010.”

Tyhee NWT Corp would like to update the MVEIRB that we expect to submit the Developers

Assessment Report (DAR) in the second quarter of 2010. The actual submission date will be

conveyed to the MVEIRB once the Pre-Feasibility Study, currently underway, is completed and

that the findings of the Pre-Feasibility Study can be incorporated into the DAR in a timely

manner.

Should you have any questions related to this matter, please contact me on my cell 780-975-2550.

Yours truly,

Original signed by H.R. Wilson

Hugh R. Wilson

Vice President–Environment and Community Affairs