Welcome To Mangazeya Mining HUB On AGORACOM

Edit this title from the Fast Facts Section

Free
Message: White Tiger Gold Increases Ore Production at Lamaque

Just pointing out that the high-lift should be completed by now..according to WTG's 26 March NR. If completed this should be providing a fairly hefty production increase of 66%. They should also have quite a decent stockpile of ore (at least 24K tonnes) to feed if there is any mining downtime in the future. To put this in context...for Q2 we should be at 2000tpd with a grade of at least 2.5gpt. This would represent around 14,000 ounces for Q2.

"With long-hole dyke stopes continuing to provide increased ore tonnages, the Company expects to see even higher production once an upgrade to a high-lift C4 conveyor in the crushing system is completed. This conveyor has constrained crushed and milled tonnages to 1200 tpd. This optimization has already begun and is scheduled for completion by mid-April, when it will permit increased production to more than 2000 tpd."

Share
New Message
Please login to post a reply