Google Inc., Nest Labs, Inc., and Dropcam, Inc. (“Petitioners”) and e. Digital Corporation (“Patent Owner”) have jointly agreed to modify the December 22, 2015 Scheduling Order (Paper 12) that the Board issued for the above captioned proceeding.
Specifically, Petitioners and Patent Owner have agreed to modify Due Dates 2 and 3 as follows:
Modified DUE DATE 2..............................June 23, 2016 now July 22, 2016
Petitioner’s reply to patent owner’s response to petition
(strike) Petitioner’s opposition to motion to amend
Modified DUE DATE 3 ............................................................July 25, 2016
(strike) Patent owner’s reply to petitioner’s opposition to motion to amend
All other DUE DATES in the Scheduling Order remain the same. Prior authorization for this Joint Stipulation was provided in the Scheduling Order. (Paper 12, p. 2.) Petitioners consulted with counsel for Patent Owner. Counsel for Patent Owner stated that they have no objection to moving the dates as shown above. It is not believed that any other action, by the parties or by the Board, is required to put the requested schedule modification into effect.