Welcome To The Mountain Province Diamonds HUB On AGORACOM

Edit this title from the Fast Facts Section

Free
AGORACOM NEWS FLASH

Dear Agoracom Family,

I want to thank all of you for your patience with us over the past 48 hours and apologize for what was admittedly a botched launch of our new site.

As you can see, we have reverted back to the previous version of the site while we address multiple forum functionality flaws that inexplicably made their way into the launch.

To this end:

1.We have identified 8 fundamental but easily fixable flaws that will be corrected in the coming week, so that you can continue to use the forums exactly as you've been accustomed to.

2.Additionally we will also be implementing a couple of design improvements to "tighten up" the look and feel of the forums.

Sincerely,

George et al

Message: Update: Mountain Province Jumped 12.9% Today, Then Provides Exploration Updates at Gahcho Kue and Kennady North

Update: Mountain Province Jumped 12.9% Today, Then Provides Exploration Updates at Gahcho Kue and Kennady North

posted on Jun 18, 2020 06:50PM

 

2020-06-18 05:05:10 PM ET (MT Newswires)
   
   

05:05 PM EDT, 06/18/2020 (MT Newswires) -- Mountain Province Diamonds Inc. (TSX: MPVD) after trade Thursday announced an update of its exploration programs for the Gahcho Kue Joint Venture, and for the company's 100%-held Kennady North Project. It noted the winter programs were planned to run from mid-February through May but were terminated in early April after declaration of the COVID-19 pandemic in March. Personnel for both programs reported no incidence of the virus during the winter operations, or during the 14-day self-quarantine period following completion of the programs. A summary of activities that were completed before termination of the winter programs is provided.

Earlier Thursday, MPVD lowered 2020 guidance for the Gahcho Kue mine to take into account the impacts of the COVID-19 pandemic. After withdrawing guidance in March, Mountain Province Diamonds said it now expects 37 million to 39 million total tonnes mined (ore and waste) for the year, down from previous guidance of 42 million to 43 million tonnes. The company also forecasts 6.3 million to 6.4 million carats recovered, compared with previous guidance of 6.75 million to 6.95 million carats.

All in cash costs are projected at $100 to $110 per tonne treated, reduced from $105 to $115 per tonne treated. Per carat recovered, all in cash costs are expected to be $50 to $55, remaining unchanged from previous guidance.

Guidance of 3.3 million to 3.4 million ore tonnes mined, as well as 3.3 million to 3.4 million ore tonnes treated, both remain unchanged as well. Meanwhile, sustaining capital expenditure was reduced to $21 million, from the previous forecast of $26.5 million.

"As a result of the all the interruptions and subsequent changes since the start of the pandemic, our total 2020 production forecast has been lowered by approximately 400K carats whilst maintaining or slightly lowering our cost guidance for full year 2020," said Stuart Brown, president and CEO of Mountain Province Diamonds. "The new forecast is the result of a tremendous amount of effort to maintain production at the mine ... We anticipate the diamond market will continue to open up over the coming months and we look forward to resuming normal sales later in the second half of the year."

Price: 0.3500, Change: +0.0400, Percent Change: +12.90

Share
New Message
Please login to post a reply