Message: Two Shallow and One Deep Drill rig?

If they have two shallow and one deep drill rig on site that is 3 rigs drilling at once. Each one can drill approx. 50 metres a day. That means that it would take approx. 9 and a half weeks more drilling to complete the next 10000 metres. or 67 days more drilling, putting us at Mid February to be done 20000 metres of drilling. Trenching would hopefully be done by then and some results would be in. All this considering that we are done the first 10000 metres or very close to being done. If they have been drilling for 90 days already with one drill, doing 50 metres a day that would only put us at the 4500 metre mark right now. Approx. 9 - 500 metre holes.

Goldenboy