Dear shareholder,
The follow response was provided by management.
1) The multi-hole drill program that started on Nov 22, 2009.
Is this on the west block or the east block or both?
We are testing new anomalies primarily in the east block
b. Multi-hole refers to - 3-5 holes or 5-8 holes or ?
Initial plan was for three holes but budget will allow for four.
c. At what depth are we drilling and will it be the same on all holes?
Holes will be terminated after the geophysical anomaly has been explained.
d. What was the reasons behind this drill program prior to the assay results?
We are meeting our flow through spending commitment for 2009.
c) Will you be reporting any visuals on the cores drilled?
Visuals would have to be extrordinary. But would be reported if material.
Regards,
AGORACOM Investor Relations