Message: Timeline? When Will Production Start?

Dear shareholder,

Thank you for your inquiry. The following response was provided by management.

Please refer to the January 25th 2010 press release where an estimate of testing was given at three months. Given the fact that we have endured hundreds of hours in Bulldozer break downs in the construction of the tailings dam, we will come very close to that estimate of January. As for full production, the mill will be steadily fed an increased amount of material daily until design throughput is obtained. You don’t just flip a switch, as we must control solids percentages and chemical balances as you increase tons through the mill. Typical mill start up to full production is three to six months.

Everything humanly possibly is being done to get La Yesca up and running as quickly as possible and the start of ramp up will be press release.