CaƱariaco Deposit in Lowest Quartile of Copper Industry Production Costs

9 Billion Pounds Copper 2 Million Ounces Gold 54 Million Ounces Silver

Free
Message: Candente Copper Files NI 43-101 Technical Report For The 2022 PEA On The Canariaco Copper Project

Candente Copper Corp. (TSX:DNT, BVL:DNT, US:CDOUF) ("Candente Copper" or "the Company") is pleased to announce that it filed on March 14th, the National Instrument ("NI") 43-101 Technical Report (the "Report") in support of the Preliminary Economic Assessment (the "2022 PEA") completed by Ausenco Engineering Canada Inc. ("Ausenco") on its Canariaco copper project in Northern Peru.

The summary of the 2022 PEA results were announced on February 8th, 2022, the effective date of the report, (see Candente Copper NR 145) and there are no material differences from those results in the report. The report can be found on SEDAR at www.sedar.com and on the Company's website at https://candentecopper.com/projects/canariaco-norte-copper-gold-silver/.

The 2022 PEA by Ausenco builds on earlier advanced engineering studies conducted from 2010 through 2014. Key highlights follow:

  • Initial CapEx of $1.04 B with throughput of 40,000 tonnes per day ("tpd") mine and plant;
  • After-tax NPV of US$1,010 M for base case of US$3.50/lb Cu, US$1,650/oz Au, US$21.50/oz Ag, and 8% discount rate;
  • After-tax NPV increases to US$1,833 M, with an IRR of 21.9% and payback of 4.5 years when using a copper price of US$4.50/lb.
  • Payback of pre-production capital in 7.1 years using base case price of US$3.50/lb Cu and 4.5 years using US$4.50/lb Cu;
  • Average annual metal production of 173 Mlb (78,543 tonnes) Cu, 31,395 oz Au, and 703,588 oz Ag during the life-of mine ("LOM");
  • Average annual metal production of 120 Mlb (54,539 tonnes) Cu, 24,375 oz Au, and 548,667 oz Ag for the first six years;
  • Average annual metal production of 193 Mlb (87,475 tonnes) Cu, 34,243 oz Au per year, and 766,753 oz Ag per year for the second mine phase, which will run for 21.4 years;
  • Average LOM metal recoveries of 88.1% for Cu, 64.7% for gold and 57.2% for silver;
  • Concentrate grades forecast to average approximately 26% Cu, 3.63 g/t Au and 84.16 g/t Ag for first six years;
  • LOM Concentrate grades are projected to average approximately 26% Cu, 3.27 g/t Au and 75.40 g/t Ag;
  • Mine and plant expansion to 80,000 tpd in year 7 with additional CapEx of $305 M from cash flow;
  • Cash operating cost of US$1.28/lb of copper including all on-site and off-site costs, treatment and refining charges ("TC/RC"), net of by-product credits;
  • Advanced ESG development strategies result in improved Infrastructure Design including a single waste management facility (WMF) with co-mingling and co-placement of waste rock and filtered mill tailings creating a smaller overall footprint further distanced from populated areas;
  • Waste to mineralized material strip ratio of 0.66:1;
  • Highly leveraged to copper prices;
  • LOM metal production of 4,848 Mlb (2,199,215 tonnes) Cu, 879,051 oz Au, and 19,700,467 oz Ag;
  • Conventional crush/grind and flotation technology;
  • Decreased OpEx with marketable concentrate with no need for arsenic treatment;
  • Pre-production capital cost of US$1.04 B is based on leased mining equipment and includes a contingency allocation of 18.5%;
  • All-in capital cost of US$1.57 B based on leased mining equipment and including life-of-mine sustaining capital, expansion capital and closure cost;
  • 28-year mine life, with potential for extension if additional resources identified below proposed pit can be included in a mine plan;
  • Located at a moderate elevation with pit centroid and process plant at approximately 3,000 metres above sea level;
  • Connection to the national power grid is planned to be by direct line approximately 55 km from the project site to the Carhuaquero substation site;
  • Significant potential for discovery of additional mineralization at nearby Canariaco Sur and Quebrada Verde targets.

The Canariaco Norte Mineral Resource estimate has been updated (see the Company's news release NR 144 dated January 28, 2022) and using a 0.15% Cu applied cut-off, which represents an approximate breakeven cut-off, contains 9.29 Blb Cu, 2.14 Moz Au and 59.43 Moz Ag in the Measured and Indicated categories as well as 2.66 Blb Cu, 0.55 Moz Au and 18 Moz Ag in the Inferred category.

Measured, Indicated and Inferred Mineral Resources were used in the 2022 PEA mine plan. Within the ultimate pit, at the $6.52/t NSR cut-off the classification breakdown of the mill feed material is 54% Measured Mineral Resources, 38% Indicated Mineral Resources and 8% Inferred Mineral Resources.

The 2022 PEA is preliminary in nature. It includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that the 2022 PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

An Inferred Mineral Resource estimate was also recently completed for a portion of Canariaco Sur which contains 2.2 Blb Cu, 1.2 Moz Au and 15 Moz Ag (NR 144), however the 2022 PEA mine plan only includes resources from Canariaco Norte.

About Candente Copper

The Company's flagship project is Canariaco, within which Canariaco Norte, is the 10th largest late-stage copper resource in the world and 6th highest in grade (RFC Ambrian, December 2021 and Haywood, December 2021). In addition to Canariaco Norte, the Canariaco Project, includes the Canariaco Sur deposit and Quebrada Verde prospect, all within a 4km NE-SW trend in northern Peru's prolific mining district.

The Company is very pleased to now have Canariaco Norte included in 4 research reports that compare various global copper projects. RFC Ambrian: Canariaco Norte in top 10 of 23 projects with potential to involve third party M&A (December 2021); Haywood: Canariaco Norte is one of 18 assets selected as likely to be considered by majors looking to acquire (December 2021); Deutsche Bank: Canariaco Norte identified as one of 3 projects required to meet the upcoming copper supply-demand gap (February 2021); Goldman Sachs: Canariaco Norte identified with incentive copper price in the lowest quartile of the top 84 copper projects worldwide (October 2018).

About Ausenco
Ausenco is a global company redefining what's possible. Its team is based across 26 offices in 14 countries, with projects in over 80 locations worldwide. Combining their deep technical expertise with a 30-year track record, Ausenco provides innovative, value-add consulting and engineering studies and project delivery, asset operations and maintenance solutions to the mining & metals, oil & gas and industrial sectors.

Joanne Freeze, P.Geo., President, CEO, Director is the Qualified Person as defined by National Instrument 43-101 for the projects discussed above. She has reviewed and approved the contents of this release.

Share
New Message
Please login to post a reply