Cliffs NEWS .. Good stuff..
posted on
Feb 03, 2011 07:40PM
NI 43-101 Update (September 2012): 11.1 Mt @ 1.68% Ni, 0.87% Cu, 0.89 gpt Pt and 3.09 gpt Pd and 0.18 gpt Au (Proven & Probable Reserves) / 8.9 Mt @ 1.10% Ni, 1.14% Cu, 1.16 gpt Pt and 3.49 gpt Pd and 0.30 gpt Au (Inferred Resource)
BMO InvestorLine Alerts
Cliffs Natural Resources Inc (CLF:NYSE) - News Alert
Cliffs Natural Resources Releases Northern Ontario Chromite Project Information to Facilitate Stakeholder Discussions
<<
>>
Cliffs Natural Resources Inc. (NYSE: CLF) (Paris: CLF) today, in connection with its ongoing discussions with stakeholders, released preliminary project information for potential development of its Black Thor chromite deposit in the McFaulds Lake or Ring of Fire area of Northern Ontario.
<<
(Logo: http://photos.prnewswire.com/prnh/20101104/CLIFFSLOGO )
>>
Cliffs Chromite Project involves the largest known North American chromite deposit, located in one of the most remote areas of Ontario, the Far North. Exploration to date has consisted of geophysics and diamond drilling to delineate the Black Thor chromite zone. The current inferred mineral resource estimate indicates the Black Thor deposit contains approximately 69.5 million tonnes at a grade of about 31.9% Cr2O3.
The project information released today presents a 'base case,' which reflects one set of realistic options for the major inter-related components of the project - from mining of the chromite ore to ferrochrome production. These 'base case' project components do not necessarily represent the final design, location or scope of the project. During the course of prefeasibility, feasibility and detailed design studies, other viable options may be identified and considered.
"Cliffs is currently conducting pre-feasibility studies to more accurately determine the viability of this project," stated Bill Boor, President, Ferroalloys. "Our work has progressed to a point that enables more detailed and meaningful stakeholder discussions that will impact our decisions about the project."
<<
The 'base case' includes the following major inter-related components:
-- An open pit chromite mine with associated housing and other proposed
infrastructure located at the site. The mine may transition to
underground mining in 10 to 15 years after mining begins. Further
testing and mine planning is required to determine the timing of a
transition to underground mining.
-- An ore processing facility to produce concentrate and associated
load-out facility located at the mine site.
-- An integrated transportation system to link all project components.
This transportation system will include a permanent all-season road to
allow the movement of people, equipment, supplies, lump ore and
concentrate to and from the proposed mine site and the existing Ontario
rail infrastructure. The evaluation to date has included a comparison
of road and rail options within several transportation corridors. The
northern extension of Road 643 from Nakina has been identified as a
realistic and viable option. Accordingly, an all-weather road in this
corridor was included in the 'base case.'
-- A ferrochrome production facility (FPF) utilizing closed electric arc
furnaces to manufacture ferrochrome. The availability of a large,
reliable, long-term and cost-competitive supply of electricity is a
requirement for the FPF. Current estimates of the furnace requirements
are approximately 300 MW. The Company has identified only a few places
in Northern Ontario where this power requirement can be met. A
brownfield site within the City of Greater Sudbury was identified as
the 'base case' location for the FPF. Cliffs has plans to continue to
meet with other northern municipalities, including Thunder Bay,
Greenstone and Timmins, to continue discussing the potential of
locating the FPF in their community.
>>
"At current provincial power rates, there isn't a location in Ontario that is economically viable for Cliffs to build the FPF. Despite this, we have named Sudbury as the 'base case' location, which we believe is representative of a technically feasible site," said Boor. "The viability of an Ontario-based FPF and final selection of the location are still being evaluated."
The pre-feasibility study for this chromite project is expected to be completed by September 2011. If the pre-feasibility report is favorable, a full feasibility study would begin immediately afterward and is expected to be completed in late 2012.
"Assuming prefeasibility and feasibility studies are favorable, we expect to begin production in 2015," Boor noted. "In order to achieve this target, we will continue our discussions with First Nations, interested individuals and all levels of government. We continue to be very excited about the potential to develop this project for the mutual benefit of Ontario, the First Nations communities and Cliffs."