Hydro One / Ring of Fire 2017
posted on
Oct 26, 2018 08:35AM
NI 43-101 Update (September 2012): 11.1 Mt @ 1.68% Ni, 0.87% Cu, 0.89 gpt Pt and 3.09 gpt Pd and 0.18 gpt Au (Proven & Probable Reserves) / 8.9 Mt @ 1.10% Ni, 1.14% Cu, 1.16 gpt Pt and 3.49 gpt Pd and 0.30 gpt Au (Inferred Resource)
This report is a more up to date look at Hydro One's Northwestern game plan:
Copy & Paste:
Draft_RIP Report_Northwest - Hydro One
PDFhttps://www.hydroone.com › Documents
The following is the summary of the currently recommended or proposed near/mid/long-term wires plans
for the sub-regions under low, medium and high load growth scenarios. The current status of these plans
is also indicated in the following.....See PAGE 8 of PDF.
On pages 34 - 36:
6.1 North of Dryden Sub-Region
Most of the demand in the North of Dryden sub-region is from the mining sector. The demand growth is
driven by the expansion of this sector, as well as the connection of up to 21 remote communities in the
northern parts of the region to Red Lake and Pickle Lake and growth in the mining sector, including
potential developments in the Ring of Fire which may be supplied from Pickle Lake.
The North of Dryden IRRP [2] for this sub-region has assumed Low, Medium (referred to as Reference in
IRRP [2]) and High load growth scenarios. Based on these scenarios, it has identified the needs and
recommended wires plans in near-term, mid-term and long-term. The following are summaries of the needs
and recommended plans for this sub-region, which consists of Pickle Lake sub-system, Red Lake sub-
system, and Ring of Fire sub-system.
6.1.1 Pickle Lake Needs and Recommended Plans
The North of Dryden IRRP [2] has identified that the existing single supply to Pickle Lake, i.e. the 115 kV
circuit E1C, is serving 24 MW of load and is at its capacity. Any load growth in the near-term from the
existing mine or connection of remote communities will require increase of LMC. The additional capacity
needs, based on the medium (reference) load growth scenario are 18 MW, 28 MW and 47 MW in near-
term, mid-term and long-term, respectively.
Pickle Lake LMC is limited by voltage stability. Providing dynamic voltage support, e.g. installing Static
VAR Compensator (SVC) at Pickle Lake offers moderate increase in LMC, assuming the remaining
capacity of circuit E4D will be available for this load increase. One alternative assessed in the IRRP is to
install a new 115 kV single-circuit line from Valora, south of Dryden, to Pickle Lake to provide additional
LMC that meets the near-term needs of Pickle Lake and releases some capacity on circuit E4D. However, in
the long-term, with the development of new mines and potential for connection of the Ring of Fire to Pickle
Lake (one the alternatives identified in the IRRP), an increase of over 130 MW in LMC may be required
under the high growth forecast. As a result, the recommendation is to proceed with a plan required to meet
the needs of the medium (reference) and high growth scenarios in the long-term. This plan can make the
full capacity of circuit E4D available to serve the Red Lake sub-system.
Recommended Plan:
• Install a new 230 kV transmission line to Pickle Lake from either the Dryden area (e.g. Dinorwic)
or Ignace area;
Install a new 230 kV switching station to connect the new line to the existing circuits D26A;
• Install a new 230/115 kV auto-transformer at the end of the new line in Pickle Lake;
• Install new 115 kV switching facilities (circuit breakers) to connect the existing circuit E1C,
existing customers at Pickle Lake and the new connections of the remote communities to the new
auto-transformer; and
• Install required reactive compensation for voltage control
An Order in Council from the government, dated July 20, 2016, has directed the OEB to amend
Wataynikaneyap Power LP’s (Watay Power) licence for Watay Power to develop and seek approvals
for the Line to Pickle Lake and the connection of sixteen remote communities. Watay Power has
initiated the Development phase of the project for these connections. Currently the planned in-service
date of the 230 kV line to Pickle Lake is Q2 2020, based on Watay Power’s active connection
assessment with the IESO.
6.1.2 Red Lake Needs and Recommended Plans
The North of Dryden IRRP [2] has identified that the current LMC of 61 MW at Red Lake, supplied by
circuits E2R and E4D, is insufficient to meet the needs of the mining load, based on the expected growth at
this location, even in near-term. The additional capacity needs, based on the medium (reference) load
growth scenario are 30 MW, 44 MW and 48 MW in near-term, mid-term and long-term, respectively.
Additional capacity needs increase to 75 MW under high load growth scenario.
The wires plans to meet the near-term needs are the following.
Recommended Plan:
• Upgrade circuit E4D to a summer rating of 660 A
• Upgrade circuit E2R to a summer rating of 610 A
• Provide additional voltage control at Ear Falls and/or Red Lake
However, since the load increase in the mining sector has not materialized at the same pace as previously
anticipated, the initial plans for the upgrade of circuits E4D and E2R have been put on hold, awaiting
customer request. A recent System Impact Assessment by the IESO for a load increase at Red Lake has
determined that although the existing system can meet the demand, circuit E4D is reaching its thermal limit.
Therefore, the above plan for the upgrade of circuit E4D (and E2R) can proceed in case of a request by, and
agreement with, customers for additional load. Alternatively, operating measures can be used until
additional firm capacity becomes available in the mid-term.
In the mid/long-term, assuming that the planned 230 kV line to Pickle Lake (see the previous section) is
completed, which can make the full capacity of circuit E4D available to serve the Red Lake sub-system,
there will be sufficient capacity to meet the needs under medium (reference) and high load growth
scenarios. Only if the needs exceed the high growth forecast of this planning horizon, or the planned 230
kV line to Pickle Lake is not completed, a new 115 kV or 230 kV line from Dryden to Ear Falls will be one
of the alternatives for meeting the demand.
6.1.3 Ring of Fire Sub-system Needs and Potential Options
The North of Dryden IRRP [2] has indicated that as the Ring of Fire sub-system is remote from the existing
transmission system, any additional capacity needs would require new facilities. The IRRP has also
indicated that transmission supply is the most economic option under all of the forecast scenarios, which
considers the five remote communities in the vicinity of the Ring of Fire that have been identified as being
economic to connect in the IESO’s Remote Community Connection Plan [6] as well as possible mining
customers. If mining load does not fully materialize, the North of Dryden IRRP [2] concluded that an east-
west supply from the Pickle Lake area was the most economic option. If mining load fully materializes, the
IRRP concluded that the economic option is either an east-west supply from the Pickle Lake area or a north-
south supply from a point along the East-West Tie. Development in the area is still at an early stage and no
firm recommendations can be made at this time.
Comment: After reading Hydro One's 2017 Draft RIP Report Northwest I get the feeling that Mushkegowuk and Quebec Hydro have a good shot at providing the power corridor for the Ring of Fire. Any attempt by Hydro One to do so does not appear to be as economic as what Mushkegowuk is proposing; at a glance. Especially if the hydro lines that run to the DeBeers Victor mine from Attawapiskat can be utilized by the Five Nations Energy group of Mushkegowuk to piggy back cheap electricity to both Matawa and the Ring of Fire. I guess the question now is how much does the continued growth of Matawa and any future mining in the Ring of Fire region mean to Hydro One. & Is the cost of running power to these remote Matawa communities and the Ring of Fire worth the expense to keep Quebec Hydro from coming across the provincial border.
TM.