Late Winter to Spring 2019

  • A Notice of Commencement of the Terms of Reference was published and distributed on March 6, 2019 (view the English or French Notice of Commencement)
  • A Notice of Public Information Centres #1 was published and distributed on April 16, 2019 (view the English or French Notice of Public Information Centres)
  • Public Information Centre #1
  • Ongoing engagement with Indigenous communities

Summer 2019

  • Initial Project Description submitted to the federal Impact Assessment Agency of Canada (the Agency)
  • Field studies conducted on alternative routes throughout Summer into 2020

Fall 2019

Winter 2019/2020

  • Public Information Centre #2
  • Draft Terms of Reference released for review by Indigenous communities, agencies, the public, and other stakeholders on December 4, 2019
  • Notice of Commencement of the IA was published by the Agency on February 24, 2020