CALGARY, July 27 /CNW/ - Petrolifera Petroleum Limited announced today that it has suspended the La Pinta No. 1 well, drilled solely by it on its 100 percent-owned Sierra Nevada License in the Lower Magdalena Basin onshore northern Colombia, after testing light gravity 44 degree API crude oil at instantaneous measured rates of up to 776 barrels per day with limited associated natural gas and no water, from a twenty-five foot perforated interval at depths between 10,695 feet and 10,720 feet at the top of the Cienaga de Oro Formation ("CDO"). Instantaneous rates are not reflective of sustainable production rates and if the La Pinta No. 1 well is remediated such that commercial production is established, these production rates may differ materially from the recorded instantaneous flow rate reflected herein.

The flow of crude oil ceased approximately 30 minutes after the above flow rate was measured. A subsequent wireline survey indicated that this likely occurred as a sand plug had formed in the well's tubing string at a depth of approximately 6,856 feet subsurface, well above the perforated interval. A coiled tubing unit was brought in to clean out the sand plug but this operation had to be discontinued due to the presence of high pressures (estimated up to 8,000 psi) below the sand plug and the lack of pressure control on the well during the coiled tubing operation.

There was evidence, including the presence of large pieces of gravel and coarse sand found in the separators and the presence of formation water with the same salinity as that recovered with crude oil in an earlier test of a lower CDO zone, which led the company to conclude that the well may have suffered a casing split, or separation, below the perforated producing interval. This could have propagated downwards from the perforations in the upper portion of the CDO due to high pressures and the fluid flow from the producing interval. The casing failure may have allowed the influx of sand and water into the well, which then terminated the flow of crude oil from the perforated interval at the top of the CDO.

The well has been suspended pending remediation of the sand problem and the drilling rig will be released to another operator for one well for approximately 120 days. The drilling rig will then be returned to Petrolifera for future exploratory drilling, likely also on the Sierra Nevada License, which the company anticipates renewing for one additional year. This renewal of the Sierra Nevada License will require a work commitment of 150 kilometers of 2D seismic and one new exploratory well, likely to be located at either the La Pinta No. 2 location on a separate shallower prospect or at Brillante, also located on the Block.

In the meantime, Petrolifera will evaluate the results of the La Pinta No. 1 well to determine its preferred course of action. The rapid influx of fine to coarse-grained sand, then gravel and the frequently high instantaneous measured flow rates recorded during the testing program of the upper perforated portion of the CDO is, in the opinion of Petrolifera's technical management, indicative of high permeability within the producing formation. It was the opinion of Petrolifera's technical management, prior to and during the drilling and test of the La Pinta No. 1 well, that the most significant identifiable risk associated with the La Pinta prospect on which the La Pinta No. 1 well was drilled was the possibility of encountering low permeability reservoirs at the CDO level. This identified risk appears to have been mitigated, although there can be no assurance that the indication of a highly permeable reservoir, based on the influx of sand and gravel and the frequently high measured flow rates of light gravity crude oil during the testing program, is satisfactory evidence of consistently high permeability over the entire indicated structure in the absence of further testing and drilling activity or that commercial production could be obtained from the well until there is a resolution of the sanding issues which arose during the testing program.

Oil gravities averaging 44 degrees API and assay data indicate that the oil is high quality. Other technical parameters indicate further efforts to complete the well and develop the indicated accumulation are warranted. Accordingly, consideration will be given to timely procurement of a lower-cost snubbing unit to conduct the remedial activity in the upper portion of the CDO. Subsequently, a service rig could be mobilized for the testing of the uphole zones above the CDO in the well, as warranted by drilling results and log analysis. It should also be noted that artificial lift would likely be required at an early stage of production, if not immediately, to produce crude oil from the upper portion of the CDO (if, as and when completed satisfactorily), due to the low indicated volumes of associated natural gas produced with the crude oil while being tested. The company views this situation to be constructive, as since the natural gas volumes are indicated to be low, flaring would likely be permitted. Accordingly, it is anticipated this would allow the company to produce crude oil from the upper portion of the CDO, without having to install high-cost natural gas handling facilities and without having to reinject natural gas back into the formation while producing crude oil from the indicated reservoir.

While this is not the ideal or preferred outcome of the La Pinta No. 1 testing program for Petrolifera, in the opinion of management the cumulative evidence of reservoir, free flowing high quality light crude oil, an indicated thick hydrocarbon-bearing section (based on drilling results, logs and some testing) and structural closure, with considerable thickness above an apparent oil/water contact, suggests considerable potential for future development and exploitation. As the drilling and testing costs of the La Pinta No. 1 well are anticipated to be approximately US$25 million, considerably over the original budget, it may in the future be prudent for the company to attract third party participation by way of farmout or other form of similar agreement with a third party, with a view to reducing the company's prospective financial and operational risks to fully and finally evaluate the related La Pinta prospect and other identified opportunities on the Sierra Nevada I License. This approach will be assessed in the near term and determined in the context of the broader range of projects currently in Petrolifera's inventory and having regard to the company's overall financial capacity.

The La Pinta No. 1 well was spudded on January 23, 2009 after a 38 day rig mobilization. The well encountered numerous drilling challenges and drilling was completed on May 6, 2009. Completion operations were commenced on May 7, 2009 but testing could not commence for fourteen days, as an alternate campsite had to be constructed due to landowner complications. Three packer failures contributed a further sixteen days to the duration of the testing program. The well will be classified as suspended on July 27, 2009.

Exploration, appraisal and development of reserves is speculative and involves a significant degree of risk. There is no guarantee that exploration or appraisal of the La Pinta No. 1 well will lead to a commercial discovery or, if there is a commercial discovery, that Petrolifera will be able to realize such reserves as intended.

Petrolifera Petroleum Limited is a Calgary-based crude oil and natural gas exploration, development and production company with operations in Argentina, Colombia and Peru. The company's main production platform is at Puesto Morales Norte in Argentina. Extensive undeveloped lands are held in all three countries, including three licenses in Peru and three blocks in Colombia.

Forward looking information:

This press release contains forward looking information including, but not limited to, the possible cause of the cessation of crude oil flow encountered at the La Pinta No. 1 well in Colombia, the planned suspension of the La Pinta No. 1 well, plans to assess the geological and drilling information from the La Pinta No. 1 well to identify possible re-entry and remediation opportunities and future exploration activities on the Sierra Nevada I License, including the anticipated renewal of the Sierra Nevada License, the anticipated drilling and testing costs of the La Pinta No. 1 well, the expected timing of the return of the rig utilized at the La Pinta No. 1 well, the possible need for artificial lift to produce oil from the CDO, possible third party participation to evaluate the Sierra Nevada I License, the ability of Petrolifera to produce crude oil from the upper portion of the CDO and exploration and development plans for the company's remaining Colombian properties. This information is based on current information and expectations that involve a number of risks and uncertainties, which could cause actual results to differ materially from those anticipated. These risks include, but are not limited to risks associated with the oil and gas industry (e.g. operational risks in development, exploration and production, delays or changes in plans with respect to exploration or development projects or capital expenditures; the uncertainty of reserve estimates; the uncertainty of estimates and projections in relation to production, costs and expenses and health, safety and environmental risks), the risk of commodity price and foreign exchange rate fluctuations, the uncertainty associated with negotiating with foreign governments and third parties located in foreign jurisdictions, risk associated with international activity and the uncertainty associated with accessing new financing to pursue exploration and development activities in South America. There can be no assurance that future exploration activities in Colombia or other countries in which the company operates will result in the discovery of commercial quantities of crude oil and/or natural gas or, if there is a commercial discovery, that Petrolifera will be able to realize such reserves as intended. Hydrocarbon shows and results of logs do not confirm the presence of commercial hydrocarbons. Additionally, exploration activities can require significant capital which may necessitate future capital raising by the company, completion of joint venture or farm-out arrangements with third parties, reprioritizing expenditures based on current capital availability or deferral of expenditures until the necessary financing is available to the company. There are risks and uncertainties associated with financing activities, negotiation with third parties and altering exploration and development activities and timelines. These risks and uncertainties are described in more detail in the company's Annual Information Form for the year ended December 31, 2008 which is available at www.sedar.com. Reference should be made to this additional information prior to making any investment decision. Additional risks and uncertainties faced by the company are described in the company's Annual Information Form for the year ended December 31, 2008 which is filed on SEDAR at www.sedar.com and readers should review these risks and uncertainties for a detailed description of the risks and uncertainties facing the company. Due to the risks, uncertainties and assumptions inherent in forward looking information, prospective investors in the company's securities should not place undue reliance on this forward looking information. Forward looking information contained in this press release is made as of the date hereof and is subject to change. The company assumes no obligation to revise or update forward looking information to reflect new circumstances, except as required by law.