or sgr's sums don't quite add up again
3rd Feb 2010 NR ~ San Gold also reports that development has commenced toward the “007” zone from the Hinge decline. Mobilization of the mining contractor Cementation took place during the first week in January and advance of approximately 20 feet per day is now underway with contract crews. This initial access drift is approximately 550 meters (1800 ft) long and is expected to reach the “007” zone late in the second quarter.
Mar 1st 2010 NR ~ Development towards the 007 Zone is underway, originating from the Hinge decline with over 660 feet (200 meters) completed to date. An additional 1,500 feet (450 meters) remain in order to access the zone at 820 feet (250 meters) vertical depth where initial development and bulk sampling of the 007 zone is anticipated to begin in the third quarter, 2010.
initial drift 550m.........then 200m completed and 450m to go, 650m...so could be just 100m done in jan+feb which means 50m per month, 9 months and a nov-dec timing..
traditional 'don't know'.