Message: Re: " I would be very surprised if SLI is around a year from now. "/Kemo

And reading further in the paragraph from where you obtained the Aug (re)submittal, it goes on to say

3.4.1 Permitting and Environmental Liabilities

An Environmental Impact Study (“E.I.S.”) is required by Peruvian law to be filed for all

exploration and development projects in the Country and acceptance is required to secure permits

necessary to conduct the requisite exploration and investigations described in this report including

exploration drilling. An E.I.S. for the Tesoro Project was completed and filed with the Peruvian

Government in early 2007, in relation to ongoing exploration and development. The time limit for

this E.I.S. expired in early 2010, and St. Elias completed and filed an updated E.I.S. in August,

2010. Currently, the Tesoro E.I.S. has been submitted to the Peruvian government and is under

review, ‘Observations” from the government review are expected by early October 2010.

My Bold highlights

Going by the recommendations of Mr. Gray, there is weeks of work o do prior to drilling. Everyone would like to see this proceed quickly but everything takes time.

3
Oct 26, 2010 08:41PM
3
Oct 26, 2010 09:34PM
2
Oct 26, 2010 09:57PM
4
Oct 29, 2010 02:50AM
2
Oct 29, 2010 04:22AM
2
Oct 29, 2010 08:02AM
2
Oct 30, 2010 01:27AM
Share
New Message
Please login to post a reply