Here's a summary of the capex costs that were included in the 2008 PFS:


Total ($M)
Mine Facilities 50.4
Primary Crushing & Coarse Ore Conveying 85.8
Coarse Ore Reclaim 125.9
Grinding & Pebble Crushing 317.5
Bulk Floatation & Regrind 133
Copper-Molybdenum Separation 6
Copper Concentrate 14.5
Molybdenum Concentrate 4.1
Tailings Handling 35.2
Tailings Pond & Water Reclaim System 17.3
Tailings Impoundment 173.3
Reagents 14.6
Plant Services 33.8
Buildings & Ancillary Facilities 39.9
Site Development 264.2
Contracted Directs 1,315.50


Common Distributables 399.1
EPCM 211
Contracted Indirects 610.1
Owner’s Cost 459.8
Subtotal 2,385.30


PST Taxes 28.6
Contingency 536.5
Total 2,950.40
Share