Content of first post did not show...
Community of Marten Falls 115 km
south of discovery, or 190 km by
proposed winter road (discussion
underway)
The Tibbitt to Contwoyto winter road’s route — a distance of 568km travels 87% of the way over frozen lakes.
Joint venture is a partnership between Echo Bay Mines Ltd., BHP Billiton, and Diavik Diamond Mines Inc.
Nuna reported an annual operational cost of $10,000.000 for 600 km
aprox $17000.00 / km
Ice road to Martin Falls from McFaulds Lake
200 km @ $17,000 = annual operational cost of $3,400,000.00 / year
Initial construction cost ?
See this report, c/o Northern Gas Project Secretariat's
its quite involved of land portions
http://www.ngps.nt.ca/Upload/Propone...
History of ice road construction
http://www.thedieselgypsy.com/Ice%20...
Nuna Logistics:
http://www.nunalogistics.com/project...
RTL ice road:
http://www.rtl.ca/index.php?option=c...